Waref Residences By Sido Development construction progress
Waref Residences By Sido Development in Jumeirah Village Circle was registered to complete in May 2026 and is still under construction. At the last site inspection, in April 2026, it was 81% built. The developer is Sido Development.
81%
Built, at the site inspection of 28 April 2026
7 months past its registered completion date
- Registered completion date
- May 2026
- Finish at recent pace
- September 2026
- Construction started
- February 2024
- First registered
- October 2024
- Developer
- Sido Development
- Community
- Jumeirah Village Circle
- Units
- 228
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- وارف ريزيدنس باي سيدو للتطوير
- Project number
- 3036
- Site inspections
- 6
Schedule
Waref Residences By Sido Development was registered to complete in May 2026, 7 months ago, and is still under construction. Over the last year of inspections it has added about 4.0 points a month. Kept at that rate, the site would reach 100% around September 2026.
Site inspections
28 April 2026
81%+10 pts
11 February 2026
71%+12 pts
27 November 2025
58%+14 pts
22 July 2025
44%+15 pts
18 April 2025
30%+17 pts
3 July 2024
12%
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
Own a unit in Waref Residences By Sido Development?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Waref Residences By Sido Development handover date?
- The registered completion date was May 2026, and the register still lists Waref Residences By Sido Development as under construction. At the pace of its recent inspections the site would reach 100% around September 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Waref Residences By Sido Development?
- Waref Residences By Sido Development was 81% built at the site inspection on 28 April 2026. The site has been inspected 6 times since July 2024. The Land Department took 45 site photos at its inspections.
- Is Waref Residences By Sido Development delayed?
- Yes. Its registered completion date of May 2026 has passed and the project is still listed as under construction.
- Who is building Waref Residences By Sido Development?
- The registered developer is Sido Development.
- Which bank holds the escrow account for Waref Residences By Sido Development?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Aliva GreenNearby in Jumeirah Village Circle. 52%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 91%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.