Waref Residences By Sido Development construction progress

Waref Residences By Sido Development in Jumeirah Village Circle is 81% built at the Land Department inspection of April 2026. Developer Sido Development. Completion registered for May 2026.

81%

Built, at the Land Department site inspection of 28 April 2026

5 months past its registered completion date

Completion date (Land Department)
May 2026
Finish at recent pace
September 2026
Construction started
February 2024
Registered with the Land Department
October 2024
Developer
Sido Development
Units
228
Escrow bank
First Abu Dhabi Bank
Name in Arabic
وارف ريزيدنس باي سيدو للتطوير
Land Department project number
3036
Land Department site inspections
6

Schedule

Waref Residences By Sido Development was registered to complete in May 2026, 5 months ago, and is still under construction. Over the last year of inspections it has added about 4.0 points a month. Kept at that rate, the site would reach 100% around September 2026.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

28 April 2026

81%+10 pts

  • Waref Residences By Sido Development construction site, Land Department inspection photo 1, 28 April 2026
  • Waref Residences By Sido Development construction site, Land Department inspection photo 2, 28 April 2026
  • Waref Residences By Sido Development construction site, Land Department inspection photo 3, 28 April 2026
  • Waref Residences By Sido Development construction site, Land Department inspection photo 4, 28 April 2026

11 February 2026

71%+12 pts

  • Waref Residences By Sido Development construction site, Land Department inspection photo 1, 11 February 2026
  • Waref Residences By Sido Development construction site, Land Department inspection photo 2, 11 February 2026
  • Waref Residences By Sido Development construction site, Land Department inspection photo 3, 11 February 2026
  • Waref Residences By Sido Development construction site, Land Department inspection photo 4, 11 February 2026

27 November 2025

58%+14 pts

  • Waref Residences By Sido Development construction site, Land Department inspection photo 1, 27 November 2025
  • Waref Residences By Sido Development construction site, Land Department inspection photo 2, 27 November 2025
  • Waref Residences By Sido Development construction site, Land Department inspection photo 3, 27 November 2025
  • Waref Residences By Sido Development construction site, Land Department inspection photo 4, 27 November 2025

22 July 2025

44%+15 pts

  • Waref Residences By Sido Development construction site, Land Department inspection photo 1, 22 July 2025
  • Waref Residences By Sido Development construction site, Land Department inspection photo 2, 22 July 2025
  • Waref Residences By Sido Development construction site, Land Department inspection photo 3, 22 July 2025
  • Waref Residences By Sido Development construction site, Land Department inspection photo 4, 22 July 2025

18 April 2025

30%+17 pts

  • Waref Residences By Sido Development construction site, Land Department inspection photo 1, 18 April 2025
  • Waref Residences By Sido Development construction site, Land Department inspection photo 2, 18 April 2025
  • Waref Residences By Sido Development construction site, Land Department inspection photo 3, 18 April 2025
  • Waref Residences By Sido Development construction site, Land Department inspection photo 4, 18 April 2025

3 July 2024

12%

  • Waref Residences By Sido Development construction site, Land Department inspection photo 1, 3 July 2024
  • Waref Residences By Sido Development construction site, Land Department inspection photo 2, 3 July 2024
  • Waref Residences By Sido Development construction site, Land Department inspection photo 3, 3 July 2024
  • Waref Residences By Sido Development construction site, Land Department inspection photo 4, 3 July 2024

All 45 site photos, by inspection date

Context

Jumeirah Village Circle has 119 projects under construction, 40% built on average.

Own a unit in Waref Residences By Sido Development?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Waref Residences By Sido Development be completed?
The completion date registered with the Dubai Land Department is May 2026. At the pace of its recent inspections the site would reach 100% around September 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Waref Residences By Sido Development is built?
81%, measured at the Land Department site inspection on 28 April 2026. The Land Department engineers have inspected the site 6 times since July 2024.
Is Waref Residences By Sido Development delayed?
Yes. Its registered completion date of May 2026 has passed and the Land Department still lists it as under construction.
Who is building Waref Residences By Sido Development?
The registered developer is Sido Development.
Which bank holds the escrow account for Waref Residences By Sido Development?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.