Waref Residences By Sido Development construction photos
45 photos taken by Dubai Land Department engineers at 6 site inspections, newest first. The percentage is how much of Waref Residences By Sido Development was built on the day of each visit.
28 April 202681% built
11 February 202671% built
27 November 202558% built
22 July 202544% built
18 April 202530% built
3 July 202412% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.