Villa Pera construction progress

The register lists Villa Pera in Jumeirah Village Circle as complete, with a registered completion date of January 2015. Its last site inspection on record was in February 2015. The developer is Five Real Estate Development.

100%

Built, at the site inspection of 5 February 2015

Construction complete

Registered completion date
January 2015
Construction started
September 2009
First registered
November 2008
Developer
Five Real Estate Development
Units
81
Escrow bank
First Abu Dhabi Bank
Name in Arabic
فيلا بيرا
Project number
723
Site inspections
7

Schedule

The register lists Villa Pera as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201020122014
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

5 February 2015

100%+42 pts

  • Villa Pera construction site, inspection photo 1, 5 February 2015
  • Villa Pera construction site, inspection photo 2, 5 February 2015
  • Villa Pera construction site, inspection photo 3, 5 February 2015
  • Villa Pera construction site, inspection photo 4, 5 February 2015

22 July 2014

58%+19 pts

  • Villa Pera construction site, inspection photo 1, 22 July 2014
  • Villa Pera construction site, inspection photo 2, 22 July 2014
  • Villa Pera construction site, inspection photo 3, 22 July 2014
  • Villa Pera construction site, inspection photo 4, 22 July 2014

7 April 2014

39%+11 pts

  • Villa Pera construction site, inspection photo 1, 7 April 2014
  • Villa Pera construction site, inspection photo 2, 7 April 2014
  • Villa Pera construction site, inspection photo 3, 7 April 2014
  • Villa Pera construction site, inspection photo 4, 7 April 2014

27 February 2014

28%+5.5 pts

  • Villa Pera construction site, inspection photo 1, 27 February 2014
  • Villa Pera construction site, inspection photo 2, 27 February 2014
  • Villa Pera construction site, inspection photo 3, 27 February 2014
  • Villa Pera construction site, inspection photo 4, 27 February 2014

15 January 2014

22%+12 pts

  • Villa Pera construction site, inspection photo 1, 15 January 2014
  • Villa Pera construction site, inspection photo 2, 15 January 2014
  • Villa Pera construction site, inspection photo 3, 15 January 2014
  • Villa Pera construction site, inspection photo 4, 15 January 2014

18 November 2013

9.5%+4.0 pts

  • Villa Pera construction site, inspection photo 1, 18 November 2013
  • Villa Pera construction site, inspection photo 2, 18 November 2013
  • Villa Pera construction site, inspection photo 3, 18 November 2013
  • Villa Pera construction site, inspection photo 4, 18 November 2013

16 June 2013

5.5%

  • Villa Pera construction site, inspection photo 1, 16 June 2013
  • Villa Pera construction site, inspection photo 2, 16 June 2013
  • Villa Pera construction site, inspection photo 3, 16 June 2013
  • Villa Pera construction site, inspection photo 4, 16 June 2013

All 56 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Own a unit in Villa Pera?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Villa Pera handover date?
Construction of Villa Pera is recorded as complete, with a registered completion date of January 2015. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Villa Pera?
Villa Pera was 100% built at the site inspection on 5 February 2015. The site has been inspected 7 times since June 2013. The Land Department took 56 site photos at its inspections.
Is Villa Pera delayed?
The register lists construction as complete.
Who is building Villa Pera?
The registered developer is Five Real Estate Development.
Which bank holds the escrow account for Villa Pera?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.