Villa Pera construction photos

56 photos from 7 site inspections, newest first. The percentage is how much of Villa Pera was built on the day of each visit.

5 February 2015100% built

22 July 201458% built

7 April 201439% built

27 February 201428% built

15 January 201422% built

18 November 20139.5% built

16 June 20135.5% built

Back to Villa Pera construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.