Tower 108 construction progress
The register lists Tower 108 in Jumeirah Village Circle as complete, with a registered completion date of March 2019. Its last site inspection on record was in March 2019. The developer is Damac Development.
100%
Built, at the site inspection of 24 March 2019
Construction complete
- Registered completion date
- March 2019
- Construction started
- June 2014
- First registered
- April 2014
- Developer
- Damac Development
- Community
- Jumeirah Village Circle
- Units
- 418
- Escrow bank
- Abu Dhabi Islamic Bank
- Name in Arabic
- تاور 108
- Project number
- 1499
- Site inspections
- 13
Schedule
The register lists Tower 108 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
24 March 2019
100%+3.2 pts
12 November 2018
97%+1.8 pts
14 May 2018
95%+4.3 pts
10 January 2018
91%+11 pts
10 August 2017
80%+14 pts
11 May 2017
66%+15 pts
25 December 2016
51%+17 pts
28 August 2016
33%+12 pts
26 April 2016
22%+6.1 pts
13 January 2016
16%+3.6 pts
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
Own a unit in Tower 108?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the Tower 108 handover date?
- Construction of Tower 108 is recorded as complete, with a registered completion date of March 2019. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on Tower 108?
- Tower 108 was 100% built at the site inspection on 24 March 2019. The site has been inspected 13 times since December 2014. The Land Department took 115 site photos at its inspections.
- Is Tower 108 delayed?
- The register lists construction as complete.
- Who is building Tower 108?
- The registered developer is Damac Development.
- Which bank holds the escrow account for Tower 108?
- Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Aliva GreenNearby in Jumeirah Village Circle. 52%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 91%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)