Tower 108 construction photos
115 photos from 13 site inspections, newest first. The percentage is how much of Tower 108 was built on the day of each visit.
24 March 2019100% built
12 November 201897% built
14 May 201895% built
10 January 201891% built
10 August 201780% built
11 May 201766% built
25 December 201651% built
28 August 201633% built
26 April 201622% built
13 January 201616% built
24 August 201512% built
15 April 20159.7% built
10 December 20148.8% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.