The Weave construction progress

The Weave in Jumeirah Village Circle is 7.6% built at the Land Department inspection of August 2026. Developer The Weave Real Estate Development. Completion registered for September 2028.

7.6%

Built, at the Land Department site inspection of 13 August 2026

Running behind its date

Completion date (Land Department)
September 2028
Finish at recent pace
November 2037
Construction started
March 2026
Registered with the Land Department
July 2025
Developer
The Weave Real Estate Development
Units
130
Escrow bank
First Abu Dhabi Bank
Name in Arabic
ذا وييف
Land Department project number
3805
Land Department site inspections
3

Schedule

Between April 2026 and August 2026 the site added about 0.7 points a month. At that rate it would finish around November 2037, more than three months after the September 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

13 August 2026

7.6%+2.8 pts

  • The Weave construction site, Land Department inspection photo 1, 13 August 2026
  • The Weave construction site, Land Department inspection photo 2, 13 August 2026
  • The Weave construction site, Land Department inspection photo 3, 13 August 2026
  • The Weave construction site, Land Department inspection photo 4, 13 August 2026

10 April 2026

4.8%+4.8 pts

  • The Weave construction site, Land Department inspection photo 1, 10 April 2026
  • The Weave construction site, Land Department inspection photo 2, 10 April 2026
  • The Weave construction site, Land Department inspection photo 3, 10 April 2026

11 June 2025

0%

  • The Weave construction site, Land Department inspection photo 1, 11 June 2025
  • The Weave construction site, Land Department inspection photo 2, 11 June 2025

All 9 site photos, by inspection date

Context

Jumeirah Village Circle has 119 projects under construction, 40% built on average. The Weave is behind that average.

Own a unit in The Weave?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will The Weave be completed?
The completion date registered with the Dubai Land Department is September 2028. At the pace of its recent inspections the site would reach 100% around November 2037. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of The Weave is built?
7.6%, measured at the Land Department site inspection on 13 August 2026. The Land Department engineers have inspected the site 3 times since June 2025.
Is The Weave delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2028.
Who is building The Weave?
The registered developer is The Weave Real Estate Development.
Which bank holds the escrow account for The Weave?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.