The Weave construction progress

The registered completion date for The Weave in Jumeirah Village Circle is September 2028. At the last site inspection, in August 2026, it was 7.6% built. The developer is The Weave Real Estate Development.

7.6%

Built, at the site inspection of 13 August 2026

Running behind its date

Registered completion date
September 2028
Finish at recent pace
November 2037
Construction started
March 2026
First registered
July 2025
Developer
The Weave Real Estate Development
Units
130
Escrow bank
First Abu Dhabi Bank
Name in Arabic
ذا وييف
Project number
3805
Site inspections
3

Schedule

Between April 2026 and August 2026 the site added about 0.7 points a month. At that rate it would finish around November 2037, more than three months after its registered date of September 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

13 August 2026

7.6%+2.8 pts

  • The Weave construction site, inspection photo 1, 13 August 2026
  • The Weave construction site, inspection photo 2, 13 August 2026
  • The Weave construction site, inspection photo 3, 13 August 2026
  • The Weave construction site, inspection photo 4, 13 August 2026

10 April 2026

4.8%+4.8 pts

  • The Weave construction site, inspection photo 1, 10 April 2026
  • The Weave construction site, inspection photo 2, 10 April 2026
  • The Weave construction site, inspection photo 3, 10 April 2026

11 June 2025

0%

  • The Weave construction site, inspection photo 1, 11 June 2025
  • The Weave construction site, inspection photo 2, 11 June 2025

All 9 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Own a unit in The Weave?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the The Weave handover date?
The registered completion date is September 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2037. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on The Weave?
The Weave was 7.6% built at the site inspection on 13 August 2026. The site has been inspected 3 times since June 2025. The Land Department took 9 site photos at its inspections.
Is The Weave delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2028.
Who is building The Weave?
The registered developer is The Weave Real Estate Development.
Which bank holds the escrow account for The Weave?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.