The Weave construction photos

9 photos taken by Dubai Land Department engineers at 3 site inspections, newest first. The percentage is how much of The Weave was built on the day of each visit.

13 August 20267.6% built

10 April 20264.8% built

11 June 20250% built

Back to The Weave construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.