The Vybe construction progress

The register lists The Vybe in Jumeirah Village Circle as complete, with a registered completion date of September 2025. Its last site inspection on record was in June 2025. The developer is Metrical Real Estate Development.

100%

Built, at the site inspection of 3 June 2025

Construction complete

Registered completion date
September 2025
Construction started
January 2023
First registered
April 2023
Units
276
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
ذا فايب
Project number
2578
Site inspections
6

Schedule

The register lists The Vybe as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20242025
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

3 June 2025

100%+11 pts

  • The Vybe construction site, inspection photo 1, 3 June 2025
  • The Vybe construction site, inspection photo 2, 3 June 2025
  • The Vybe construction site, inspection photo 3, 3 June 2025
  • The Vybe construction site, inspection photo 4, 3 June 2025

10 December 2024

89%+18 pts

  • The Vybe construction site, inspection photo 1, 10 December 2024
  • The Vybe construction site, inspection photo 2, 10 December 2024
  • The Vybe construction site, inspection photo 3, 10 December 2024
  • The Vybe construction site, inspection photo 4, 10 December 2024

21 August 2024

71%+30 pts

  • The Vybe construction site, inspection photo 1, 21 August 2024
  • The Vybe construction site, inspection photo 2, 21 August 2024
  • The Vybe construction site, inspection photo 3, 21 August 2024
  • The Vybe construction site, inspection photo 4, 21 August 2024

26 February 2024

41%+22 pts

  • The Vybe construction site, inspection photo 1, 26 February 2024
  • The Vybe construction site, inspection photo 2, 26 February 2024
  • The Vybe construction site, inspection photo 3, 26 February 2024
  • The Vybe construction site, inspection photo 4, 26 February 2024

4 September 2023

19%+15 pts

  • The Vybe construction site, inspection photo 1, 4 September 2023
  • The Vybe construction site, inspection photo 2, 4 September 2023
  • The Vybe construction site, inspection photo 3, 4 September 2023
  • The Vybe construction site, inspection photo 4, 4 September 2023

22 February 2023

4.0%

  • The Vybe construction site, inspection photo 1, 22 February 2023
  • The Vybe construction site, inspection photo 2, 22 February 2023
  • The Vybe construction site, inspection photo 3, 22 February 2023
  • The Vybe construction site, inspection photo 4, 22 February 2023

All 49 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Metrical Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Vybe?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the The Vybe handover date?
Construction of The Vybe is recorded as complete, with a registered completion date of September 2025. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on The Vybe?
The Vybe was 100% built at the site inspection on 3 June 2025. The site has been inspected 6 times since February 2023. The Land Department took 49 site photos at its inspections.
Is The Vybe delayed?
The register lists construction as complete.
Who is building The Vybe?
The registered developer is Metrical Real Estate Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for The Vybe?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.