Leven Residences construction progress

The registered completion date for Leven Residences in Jumeirah Village Triangle is November 2027. At the last site inspection, in August 2026, it was 23% built. The developer is Metrical Real Estate Development.

23%

Built, at the site inspection of 6 August 2026

Running behind its date

Registered completion date
November 2027
Finish at recent pace
July 2029
Construction started
April 2025
First registered
April 2025
Developer
Metrical Real Estate Development
Units
228
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
ليفين ريزيدينسز
Project number
3555
Site inspections
4

Schedule

Between December 2025 and August 2026 the site added about 2.1 points a month. At that rate it would finish around July 2029, more than three months after its registered date of November 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

6 August 2026

23%+11 pts

  • Leven Residences construction site, inspection photo 1, 6 August 2026
  • Leven Residences construction site, inspection photo 2, 6 August 2026
  • Leven Residences construction site, inspection photo 3, 6 August 2026
  • Leven Residences construction site, inspection photo 4, 6 August 2026

16 April 2026

13%+5.4 pts

  • Leven Residences construction site, inspection photo 1, 16 April 2026
  • Leven Residences construction site, inspection photo 2, 16 April 2026
  • Leven Residences construction site, inspection photo 3, 16 April 2026
  • Leven Residences construction site, inspection photo 4, 16 April 2026

23 December 2025

7.4%+7.4 pts

  • Leven Residences construction site, inspection photo 1, 23 December 2025
  • Leven Residences construction site, inspection photo 2, 23 December 2025
  • Leven Residences construction site, inspection photo 3, 23 December 2025

3 March 2025

0%

  • Leven Residences construction site, inspection photo 1, 3 March 2025
  • Leven Residences construction site, inspection photo 2, 3 March 2025

All 18 site photos, by inspection date

Context

Jumeirah Village Triangle has 29 projects under construction, 27% built on average.

Metrical Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Leven Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Leven Residences handover date?
The registered completion date is November 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Leven Residences?
Leven Residences was 23% built at the site inspection on 6 August 2026. The site has been inspected 4 times since March 2025. The Land Department took 18 site photos at its inspections.
Is Leven Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of November 2027.
Who is building Leven Residences?
The registered developer is Metrical Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Leven Residences?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.