Leven Residences construction progress
The registered completion date for Leven Residences in Jumeirah Village Triangle is November 2027. At the last site inspection, in August 2026, it was 23% built. The developer is Metrical Real Estate Development.
23%
Built, at the site inspection of 6 August 2026
Running behind its date
- Registered completion date
- November 2027
- Finish at recent pace
- July 2029
- Construction started
- April 2025
- First registered
- April 2025
- Developer
- Metrical Real Estate Development
- Community
- Jumeirah Village Triangle
- Units
- 228
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- ليفين ريزيدينسز
- Project number
- 3555
- Site inspections
- 4
Schedule
Between December 2025 and August 2026 the site added about 2.1 points a month. At that rate it would finish around July 2029, more than three months after its registered date of November 2027.
Site inspections
6 August 2026
23%+11 pts
16 April 2026
13%+5.4 pts
23 December 2025
7.4%+7.4 pts
3 March 2025
0%
Context
Jumeirah Village Triangle has 29 projects under construction, 27% built on average.
Metrical Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Leven Residences?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Leven Residences handover date?
- The registered completion date is November 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Leven Residences?
- Leven Residences was 23% built at the site inspection on 6 August 2026. The site has been inspected 4 times since March 2025. The Land Department took 18 site photos at its inspections.
- Is Leven Residences delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of November 2027.
- Who is building Leven Residences?
- The registered developer is Metrical Real Estate Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Leven Residences?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- S'Vn ResidencesAlso by Metrical Real Estate Development. 0%, Due December 2028.
- Paradise OneNearby in Jumeirah Village Triangle. 70%, Due April 2027.
- Silver StallionsNearby in Jumeirah Village Triangle. 12%, Due December 2017, passed.
- Fashionz 1 By DanubeNearby in Jumeirah Village Triangle. 40%.
- Volga TowerNearby in Jumeirah Village Triangle. 51%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpg&w=3840&q=75)