The Residence By Prestige One construction progress

The register lists The Residence By Prestige One in Jumeirah Village Circle as complete, with a registered completion date of November 2025. Its last site inspection on record was in March 2026. The developer is Prestige One Luxury Real Estate.

100%

Built, at the site inspection of 25 March 2026

Construction complete

Registered completion date
November 2025
Construction started
September 2023
First registered
August 2023
Developer
Prestige One Luxury Real Estate
Units
98
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
ذا ريزيدنس من برستيج وان
Project number
2681
Site inspections
8

Schedule

The register lists The Residence By Prestige One as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

25 March 2026

100%+17 pts

  • The Residence By Prestige One construction site, inspection photo 1, 25 March 2026
  • The Residence By Prestige One construction site, inspection photo 2, 25 March 2026
  • The Residence By Prestige One construction site, inspection photo 3, 25 March 2026
  • The Residence By Prestige One construction site, inspection photo 4, 25 March 2026

16 September 2025

83%+23 pts

  • The Residence By Prestige One construction site, inspection photo 1, 16 September 2025
  • The Residence By Prestige One construction site, inspection photo 2, 16 September 2025
  • The Residence By Prestige One construction site, inspection photo 3, 16 September 2025
  • The Residence By Prestige One construction site, inspection photo 4, 16 September 2025

28 April 2025

60%+13 pts

  • The Residence By Prestige One construction site, inspection photo 1, 28 April 2025
  • The Residence By Prestige One construction site, inspection photo 2, 28 April 2025
  • The Residence By Prestige One construction site, inspection photo 3, 28 April 2025
  • The Residence By Prestige One construction site, inspection photo 4, 28 April 2025

5 February 2025

48%+28 pts

  • The Residence By Prestige One construction site, inspection photo 1, 5 February 2025
  • The Residence By Prestige One construction site, inspection photo 2, 5 February 2025
  • The Residence By Prestige One construction site, inspection photo 3, 5 February 2025
  • The Residence By Prestige One construction site, inspection photo 4, 5 February 2025

24 October 2024

20%+10 pts

  • The Residence By Prestige One construction site, inspection photo 1, 24 October 2024
  • The Residence By Prestige One construction site, inspection photo 2, 24 October 2024
  • The Residence By Prestige One construction site, inspection photo 3, 24 October 2024
  • The Residence By Prestige One construction site, inspection photo 4, 24 October 2024

4 July 2024

10%+8.5 pts

  • The Residence By Prestige One construction site, inspection photo 1, 4 July 2024
  • The Residence By Prestige One construction site, inspection photo 2, 4 July 2024
  • The Residence By Prestige One construction site, inspection photo 3, 4 July 2024

14 March 2024

1.5%+1.5 pts

  • The Residence By Prestige One construction site, inspection photo 1, 14 March 2024
  • The Residence By Prestige One construction site, inspection photo 2, 14 March 2024
  • The Residence By Prestige One construction site, inspection photo 3, 14 March 2024
  • The Residence By Prestige One construction site, inspection photo 4, 14 March 2024

7 June 2023

0%

  • The Residence By Prestige One construction site, inspection photo 1, 7 June 2023
  • The Residence By Prestige One construction site, inspection photo 2, 7 June 2023
  • The Residence By Prestige One construction site, inspection photo 3, 7 June 2023

All 49 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Own a unit in The Residence By Prestige One?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the The Residence By Prestige One handover date?
Construction of The Residence By Prestige One is recorded as complete, with a registered completion date of November 2025. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on The Residence By Prestige One?
The Residence By Prestige One was 100% built at the site inspection on 25 March 2026. The site has been inspected 8 times since June 2023. The Land Department took 49 site photos at its inspections.
Is The Residence By Prestige One delayed?
The register lists construction as complete.
Who is building The Residence By Prestige One?
The registered developer is Prestige One Luxury Real Estate.
Which bank holds the escrow account for The Residence By Prestige One?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.