The Residence By Prestige One construction photos

49 photos from 8 site inspections, newest first. The percentage is how much of The Residence By Prestige One was built on the day of each visit.

25 March 2026100% built

16 September 202583% built

28 April 202560% built

5 February 202548% built

24 October 202420% built

4 July 202410% built

14 March 20241.5% built

7 June 20230% built

Back to The Residence By Prestige One construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.