The Orchard Place construction progress

The Orchard Place in Jumeirah Village Circle was registered to complete in July 2026 and is still under construction. At the last site inspection, in April 2026, it was 43% built. The developer is Peak Summit Real Estate Development.

43%

Built, at the site inspection of 13 April 2026

4 months past its registered completion date

Registered completion date
July 2026
Construction started
July 2023
First registered
July 2023
Units
418
Escrow bank
First Abu Dhabi Bank
Name in Arabic
ذا أوركارد بليس
Project number
2629
Site inspections
9

Schedule

The Orchard Place was registered to complete in July 2026, 4 months ago, and is still under construction. The inspections on record are too close together or show no gain, so there is no pace to project a finish from.

0%25%50%75%100%202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

13 April 2026

43%

  • The Orchard Place construction site, inspection photo 1, 13 April 2026
  • The Orchard Place construction site, inspection photo 2, 13 April 2026
  • The Orchard Place construction site, inspection photo 3, 13 April 2026

11 March 2026

43%

  • The Orchard Place construction site, inspection photo 1, 11 March 2026
  • The Orchard Place construction site, inspection photo 2, 11 March 2026
  • The Orchard Place construction site, inspection photo 3, 11 March 2026
  • The Orchard Place construction site, inspection photo 4, 11 March 2026

19 November 2025

43%

  • The Orchard Place construction site, inspection photo 1, 19 November 2025
  • The Orchard Place construction site, inspection photo 2, 19 November 2025
  • The Orchard Place construction site, inspection photo 3, 19 November 2025
  • The Orchard Place construction site, inspection photo 4, 19 November 2025

14 July 2025

43%+6.0 pts

  • The Orchard Place construction site, inspection photo 1, 14 July 2025
  • The Orchard Place construction site, inspection photo 2, 14 July 2025
  • The Orchard Place construction site, inspection photo 3, 14 July 2025
  • The Orchard Place construction site, inspection photo 4, 14 July 2025

10 February 2025

37%+6.6 pts

  • The Orchard Place construction site, inspection photo 1, 10 February 2025
  • The Orchard Place construction site, inspection photo 2, 10 February 2025
  • The Orchard Place construction site, inspection photo 3, 10 February 2025
  • The Orchard Place construction site, inspection photo 4, 10 February 2025

23 October 2024

30%+9.0 pts

  • The Orchard Place construction site, inspection photo 1, 23 October 2024
  • The Orchard Place construction site, inspection photo 2, 23 October 2024
  • The Orchard Place construction site, inspection photo 3, 23 October 2024
  • The Orchard Place construction site, inspection photo 4, 23 October 2024

6 June 2024

21%+16 pts

  • The Orchard Place construction site, inspection photo 1, 6 June 2024
  • The Orchard Place construction site, inspection photo 2, 6 June 2024
  • The Orchard Place construction site, inspection photo 3, 6 June 2024
  • The Orchard Place construction site, inspection photo 4, 6 June 2024

20 November 2023

5.1%+5.1 pts

  • The Orchard Place construction site, inspection photo 1, 20 November 2023
  • The Orchard Place construction site, inspection photo 2, 20 November 2023
  • The Orchard Place construction site, inspection photo 3, 20 November 2023
  • The Orchard Place construction site, inspection photo 4, 20 November 2023

25 April 2023

0%

  • The Orchard Place construction site, inspection photo 1, 25 April 2023

All 45 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Peak Summit Real Estate Development has 3 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in The Orchard Place?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the The Orchard Place handover date?
The registered completion date was July 2026, and the register still lists The Orchard Place as under construction. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on The Orchard Place?
The Orchard Place was 43% built at the site inspection on 13 April 2026. The site has been inspected 9 times since April 2023. The Land Department took 45 site photos at its inspections.
Is The Orchard Place delayed?
Yes. Its registered completion date of July 2026 has passed and the project is still listed as under construction.
Who is building The Orchard Place?
The registered developer is Peak Summit Real Estate Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for The Orchard Place?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.