The Orchard Place construction photos
45 photos taken by Dubai Land Department engineers at 9 site inspections, newest first. The percentage is how much of The Orchard Place was built on the day of each visit.
13 April 202643% built
11 March 202643% built
19 November 202543% built
14 July 202543% built
10 February 202537% built
23 October 202430% built
6 June 202421% built
20 November 20235.1% built
25 April 20230% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.