The Autograph-S Series construction progress

The registered completion date for The Autograph-S Series in Jumeirah Village Circle is December 2027. At the last site inspection, in April 2026, it was 19% built. The developer is Green Properties Development Co.

19%

Built, at the site inspection of 14 April 2026

Running behind its date

Registered completion date
December 2027
Finish at recent pace
May 2029
Construction started
October 2024
First registered
December 2024
Developer
Green Properties Development Co
Units
253
Escrow bank
Mashreq Bank
Name in Arabic
ذا اوتوجراف - ايس سيريس
Project number
3186
Site inspections
3

Schedule

Between October 2025 and April 2026 the site added about 2.2 points a month. At that rate it would finish around May 2029, more than three months after its registered date of December 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

14 April 2026

19%+14 pts

  • The Autograph-S Series construction site, inspection photo 1, 14 April 2026
  • The Autograph-S Series construction site, inspection photo 2, 14 April 2026
  • The Autograph-S Series construction site, inspection photo 3, 14 April 2026
  • The Autograph-S Series construction site, inspection photo 4, 14 April 2026

7 October 2025

4.7%+4.7 pts

  • The Autograph-S Series construction site, inspection photo 1, 7 October 2025
  • The Autograph-S Series construction site, inspection photo 2, 7 October 2025
  • The Autograph-S Series construction site, inspection photo 3, 7 October 2025
  • The Autograph-S Series construction site, inspection photo 4, 7 October 2025

6 August 2024

0%

  • The Autograph-S Series construction site, inspection photo 1, 6 August 2024
  • The Autograph-S Series construction site, inspection photo 2, 6 August 2024
  • The Autograph-S Series construction site, inspection photo 3, 6 August 2024

All 14 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Green Properties Development Co has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Autograph-S Series?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the The Autograph-S Series handover date?
The registered completion date is December 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on The Autograph-S Series?
The Autograph-S Series was 19% built at the site inspection on 14 April 2026. The site has been inspected 3 times since August 2024. The Land Department took 14 site photos at its inspections.
Is The Autograph-S Series delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
Who is building The Autograph-S Series?
The registered developer is Green Properties Development Co. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for The Autograph-S Series?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.