The Autograph-I Series construction progress

The Autograph-I Series in Jumeirah Village Circle is 4.0% built at the Land Department inspection of April 2026. Developer Green Properties Development Co. Completion registered for August 2028.

4.0%

Built, at the Land Department site inspection of 23 April 2026

Running behind its date

Completion date (Land Department)
August 2028
Finish at recent pace
May 2053
Construction started
March 2025
Registered with the Land Department
March 2025
Developer
Green Properties Development Co
Units
272
Escrow bank
Mashreq Bank
Name in Arabic
ذا اوتوجراف-ائي سيريس
Land Department project number
3187
Land Department site inspections
3

Schedule

Between March 2025 and April 2026 the site added about 0.3 points a month. At that rate it would finish around May 2053, more than three months after the August 2028 date registered with the Land Department.

0%25%50%75%100%2025202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

23 April 2026

4.0%+4.0 pts

  • The Autograph-I Series construction site, Land Department inspection photo 1, 23 April 2026
  • The Autograph-I Series construction site, Land Department inspection photo 2, 23 April 2026
  • The Autograph-I Series construction site, Land Department inspection photo 3, 23 April 2026
  • The Autograph-I Series construction site, Land Department inspection photo 4, 23 April 2026

10 March 2025

0%

  • The Autograph-I Series construction site, Land Department inspection photo 1, 10 March 2025
  • The Autograph-I Series construction site, Land Department inspection photo 2, 10 March 2025

6 August 2024

0%

  • The Autograph-I Series construction site, Land Department inspection photo 1, 6 August 2024
  • The Autograph-I Series construction site, Land Department inspection photo 2, 6 August 2024
  • The Autograph-I Series construction site, Land Department inspection photo 3, 6 August 2024
  • The Autograph-I Series construction site, Land Department inspection photo 4, 6 August 2024

All 10 site photos, by inspection date

Context

Jumeirah Village Circle has 119 projects under construction, 40% built on average.

Green Properties Development Co has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Autograph-I Series?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will The Autograph-I Series be completed?
The completion date registered with the Dubai Land Department is August 2028. At the pace of its recent inspections the site would reach 100% around May 2053. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of The Autograph-I Series is built?
4.0%, measured at the Land Department site inspection on 23 April 2026. The Land Department engineers have inspected the site 3 times since August 2024.
Is The Autograph-I Series delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2028.
Who is building The Autograph-I Series?
The registered developer is Green Properties Development Co. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for The Autograph-I Series?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.