The Autograph-I Series construction progress

The registered completion date for The Autograph-I Series in Jumeirah Village Circle is August 2028. At the last site inspection, in April 2026, it was 4.0% built. The developer is Green Properties Development Co.

4.0%

Built, at the site inspection of 23 April 2026

Running behind its date

Registered completion date
August 2028
Finish at recent pace
May 2053
Construction started
March 2025
First registered
March 2025
Developer
Green Properties Development Co
Units
272
Escrow bank
Mashreq Bank
Name in Arabic
ذا اوتوجراف-ائي سيريس
Project number
3187
Site inspections
3

Schedule

Between March 2025 and April 2026 the site added about 0.3 points a month. At that rate it would finish around May 2053, more than three months after its registered date of August 2028.

0%25%50%75%100%2025202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

23 April 2026

4.0%+4.0 pts

  • The Autograph-I Series construction site, inspection photo 1, 23 April 2026
  • The Autograph-I Series construction site, inspection photo 2, 23 April 2026
  • The Autograph-I Series construction site, inspection photo 3, 23 April 2026
  • The Autograph-I Series construction site, inspection photo 4, 23 April 2026

10 March 2025

0%

  • The Autograph-I Series construction site, inspection photo 1, 10 March 2025
  • The Autograph-I Series construction site, inspection photo 2, 10 March 2025

6 August 2024

0%

  • The Autograph-I Series construction site, inspection photo 1, 6 August 2024
  • The Autograph-I Series construction site, inspection photo 2, 6 August 2024
  • The Autograph-I Series construction site, inspection photo 3, 6 August 2024
  • The Autograph-I Series construction site, inspection photo 4, 6 August 2024

All 10 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Green Properties Development Co has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Autograph-I Series?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the The Autograph-I Series handover date?
The registered completion date is August 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2053. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on The Autograph-I Series?
The Autograph-I Series was 4.0% built at the site inspection on 23 April 2026. The site has been inspected 3 times since August 2024. The Land Department took 10 site photos at its inspections.
Is The Autograph-I Series delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2028.
Who is building The Autograph-I Series?
The registered developer is Green Properties Development Co. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for The Autograph-I Series?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.