Tetris Tower construction progress

The registered completion date for Tetris Tower in Jumeirah Village Circle is September 2027. At the last site inspection, in November 2026, it was 12% built. The developer is Le Luminous Real Estate Development.

12%

Built, at the site inspection of 16 November 2026

Running behind its date

Registered completion date
September 2027
Finish at recent pace
November 2036
Construction started
April 2025
First registered
January 2026
Developer
Le Luminous Real Estate Development
Units
205
Escrow bank
Mashreq Bank
Name in Arabic
تيتريس تاور
Project number
3646
Site inspections
4

Schedule

Between March 2026 and November 2026 the site added about 0.7 points a month. At that rate it would finish around November 2036, more than three months after its registered date of September 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

16 November 2026

12%+4.2 pts

  • Tetris Tower construction site, inspection photo 1, 16 November 2026
  • Tetris Tower construction site, inspection photo 2, 16 November 2026
  • Tetris Tower construction site, inspection photo 3, 16 November 2026
  • Tetris Tower construction site, inspection photo 4, 16 November 2026

30 July 2026

8.1%+1.5 pts

  • Tetris Tower construction site, inspection photo 1, 30 July 2026
  • Tetris Tower construction site, inspection photo 2, 30 July 2026
  • Tetris Tower construction site, inspection photo 3, 30 July 2026
  • Tetris Tower construction site, inspection photo 4, 30 July 2026

26 March 2026

6.6%+6.6 pts

  • Tetris Tower construction site, inspection photo 1, 26 March 2026
  • Tetris Tower construction site, inspection photo 2, 26 March 2026
  • Tetris Tower construction site, inspection photo 3, 26 March 2026
  • Tetris Tower construction site, inspection photo 4, 26 March 2026

3 April 2025

0%

  • Tetris Tower construction site, inspection photo 1, 3 April 2025
  • Tetris Tower construction site, inspection photo 2, 3 April 2025

All 16 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Own a unit in Tetris Tower?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Tetris Tower handover date?
The registered completion date is September 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2036. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Tetris Tower?
Tetris Tower was 12% built at the site inspection on 16 November 2026. The site has been inspected 4 times since April 2025. The Land Department took 16 site photos at its inspections.
Is Tetris Tower delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2027.
Who is building Tetris Tower?
The registered developer is Le Luminous Real Estate Development.
Which bank holds the escrow account for Tetris Tower?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.