Tetris Tower construction progress
Tetris Tower in Jumeirah Village Circle is 8.1% built at the Land Department inspection of July 2026. Developer Le Luminous Real Estate Development. Completion registered for September 2027.
8.1%
Built, at the Land Department site inspection of 30 July 2026
Running behind its date
- Completion date (Land Department)
- September 2027
- Finish at recent pace
- September 2047
- Construction started
- April 2025
- Registered with the Land Department
- January 2026
- Developer
- Le Luminous Real Estate Development
- Community
- Jumeirah Village Circle
- Units
- 205
- Escrow bank
- Mashreq Bank
- Name in Arabic
- تيتريس تاور
- Land Department project number
- 3646
- Land Department site inspections
- 3
Schedule
Between March 2026 and July 2026 the site added about 0.4 points a month. At that rate it would finish around September 2047, more than three months after the September 2027 date registered with the Land Department.
Site inspections
30 July 2026
8.1%+1.5 pts
26 March 2026
6.6%+6.6 pts
3 April 2025
0%
Context
Jumeirah Village Circle has 119 projects under construction, 40% built on average.
Own a unit in Tetris Tower?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Tetris Tower be completed?
- The completion date registered with the Dubai Land Department is September 2027. At the pace of its recent inspections the site would reach 100% around September 2047. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Tetris Tower is built?
- 8.1%, measured at the Land Department site inspection on 30 July 2026. The Land Department engineers have inspected the site 3 times since April 2025.
- Is Tetris Tower delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2027.
- Who is building Tetris Tower?
- The registered developer is Le Luminous Real Estate Development.
- Which bank holds the escrow account for Tetris Tower?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 42%, Due January 2013, passed.
- Serenity Lakes 2Nearby in Jumeirah Village Circle. 50%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 90%, Due April 2026, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.