Tetris Tower construction progress
The registered completion date for Tetris Tower in Jumeirah Village Circle is September 2027. At the last site inspection, in November 2026, it was 12% built. The developer is Le Luminous Real Estate Development.
12%
Built, at the site inspection of 16 November 2026
Running behind its date
- Registered completion date
- September 2027
- Finish at recent pace
- November 2036
- Construction started
- April 2025
- First registered
- January 2026
- Developer
- Le Luminous Real Estate Development
- Community
- Jumeirah Village Circle
- Units
- 205
- Escrow bank
- Mashreq Bank
- Name in Arabic
- تيتريس تاور
- Project number
- 3646
- Site inspections
- 4
Schedule
Between March 2026 and November 2026 the site added about 0.7 points a month. At that rate it would finish around November 2036, more than three months after its registered date of September 2027.
Site inspections
16 November 2026
12%+4.2 pts
30 July 2026
8.1%+1.5 pts
26 March 2026
6.6%+6.6 pts
3 April 2025
0%
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
Own a unit in Tetris Tower?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Tetris Tower handover date?
- The registered completion date is September 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2036. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Tetris Tower?
- Tetris Tower was 12% built at the site inspection on 16 November 2026. The site has been inspected 4 times since April 2025. The Land Department took 16 site photos at its inspections.
- Is Tetris Tower delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2027.
- Who is building Tetris Tower?
- The registered developer is Le Luminous Real Estate Development.
- Which bank holds the escrow account for Tetris Tower?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Aliva GreenNearby in Jumeirah Village Circle. 52%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 91%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)