Shamal Terraces 4 construction progress

The register lists Shamal Terraces 4 in Jumeirah Village Circle as complete, with a registered completion date of June 2016. Its last site inspection on record was in August 2016. The developer is Lootah Real Estate Development.

100%

Built, at the site inspection of 24 August 2016

Construction complete

Registered completion date
June 2016
Construction started
January 2014
First registered
March 2014
Developer
Lootah Real Estate Development
Units
9
Escrow bank
Dubai Islamic Bank
Name in Arabic
شمال تراس 4
Project number
1498
Site inspections
3

Schedule

The register lists Shamal Terraces 4 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20152016
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

24 August 2016

100%+40 pts

  • Shamal Terraces 4 construction site, inspection photo 1, 24 August 2016
  • Shamal Terraces 4 construction site, inspection photo 2, 24 August 2016
  • Shamal Terraces 4 construction site, inspection photo 3, 24 August 2016
  • Shamal Terraces 4 construction site, inspection photo 4, 24 August 2016

1 October 2015

60%+53 pts

  • Shamal Terraces 4 construction site, inspection photo 1, 1 October 2015
  • Shamal Terraces 4 construction site, inspection photo 2, 1 October 2015
  • Shamal Terraces 4 construction site, inspection photo 3, 1 October 2015

31 December 2014

7.3%

  • Shamal Terraces 4 construction site, inspection photo 1, 31 December 2014
  • Shamal Terraces 4 construction site, inspection photo 2, 31 December 2014

All 12 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Own a unit in Shamal Terraces 4?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Shamal Terraces 4 handover date?
Construction of Shamal Terraces 4 is recorded as complete, with a registered completion date of June 2016. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Shamal Terraces 4?
Shamal Terraces 4 was 100% built at the site inspection on 24 August 2016. The site has been inspected 3 times since December 2014. The Land Department took 12 site photos at its inspections.
Is Shamal Terraces 4 delayed?
The register lists construction as complete.
Who is building Shamal Terraces 4?
The registered developer is Lootah Real Estate Development.
Which bank holds the escrow account for Shamal Terraces 4?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.