Sereno Residences construction progress

Sereno Residences in Jumeirah Village Circle was registered to complete in September 2026 and is still under construction. At the last site inspection, in October 2026, it was 32% built. The developer is Svarn Real Estate Development.

32%

Built, at the site inspection of 28 October 2026

3 months past its registered completion date

Registered completion date
September 2026
Finish at recent pace
February 2029
Construction started
September 2024
First registered
July 2024
Developer
Svarn Real Estate Development
Units
94
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
سيرينو ريزيدنسز
Project number
3078
Site inspections
9

Schedule

Sereno Residences was registered to complete in September 2026, 3 months ago, and is still under construction. Over the last year of inspections it has added about 2.5 points a month. Kept at that rate, the site would reach 100% around February 2029.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

28 October 2026

32%+9.6 pts

  • Sereno Residences construction site, inspection photo 1, 28 October 2026
  • Sereno Residences construction site, inspection photo 2, 28 October 2026
  • Sereno Residences construction site, inspection photo 3, 28 October 2026
  • Sereno Residences construction site, inspection photo 4, 28 October 2026

3 August 2026

22%+7.2 pts

  • Sereno Residences construction site, inspection photo 1, 3 August 2026
  • Sereno Residences construction site, inspection photo 2, 3 August 2026
  • Sereno Residences construction site, inspection photo 3, 3 August 2026
  • Sereno Residences construction site, inspection photo 4, 3 August 2026

28 April 2026

15%+5.9 pts

  • Sereno Residences construction site, inspection photo 1, 28 April 2026
  • Sereno Residences construction site, inspection photo 2, 28 April 2026
  • Sereno Residences construction site, inspection photo 3, 28 April 2026
  • Sereno Residences construction site, inspection photo 4, 28 April 2026

20 January 2026

9.4%+6.3 pts

  • Sereno Residences construction site, inspection photo 1, 20 January 2026
  • Sereno Residences construction site, inspection photo 2, 20 January 2026
  • Sereno Residences construction site, inspection photo 3, 20 January 2026
  • Sereno Residences construction site, inspection photo 4, 20 January 2026

22 September 2025

3.1%+0.1 pts

  • Sereno Residences construction site, inspection photo 1, 22 September 2025
  • Sereno Residences construction site, inspection photo 2, 22 September 2025
  • Sereno Residences construction site, inspection photo 3, 22 September 2025

29 May 2025

3.0%+0.3 pts

  • Sereno Residences construction site, inspection photo 1, 29 May 2025
  • Sereno Residences construction site, inspection photo 2, 29 May 2025
  • Sereno Residences construction site, inspection photo 3, 29 May 2025

21 January 2025

2.7%+2.1 pts

  • Sereno Residences construction site, inspection photo 1, 21 January 2025
  • Sereno Residences construction site, inspection photo 2, 21 January 2025
  • Sereno Residences construction site, inspection photo 3, 21 January 2025

4 October 2024

0.6%+0.6 pts

  • Sereno Residences construction site, inspection photo 1, 4 October 2024
  • Sereno Residences construction site, inspection photo 2, 4 October 2024
  • Sereno Residences construction site, inspection photo 3, 4 October 2024
  • Sereno Residences construction site, inspection photo 4, 4 October 2024

28 May 2024

0%

  • Sereno Residences construction site, inspection photo 1, 28 May 2024
  • Sereno Residences construction site, inspection photo 2, 28 May 2024
  • Sereno Residences construction site, inspection photo 3, 28 May 2024

All 41 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Own a unit in Sereno Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Sereno Residences handover date?
The registered completion date was September 2026, and the register still lists Sereno Residences as under construction. At the pace of its recent inspections the site would reach 100% around February 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Sereno Residences?
Sereno Residences was 32% built at the site inspection on 28 October 2026. The site has been inspected 9 times since May 2024. The Land Department took 41 site photos at its inspections.
Is Sereno Residences delayed?
Yes. Its registered completion date of September 2026 has passed and the project is still listed as under construction.
Who is building Sereno Residences?
The registered developer is Svarn Real Estate Development.
Which bank holds the escrow account for Sereno Residences?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.