Sereno Residences construction progress

Sereno Residences in Jumeirah Village Circle is 22% built at the Land Department inspection of August 2026. Developer Svarn Real Estate Development. Completion registered for September 2026.

22%

Built, at the Land Department site inspection of 3 August 2026

1 months past its registered completion date

Completion date (Land Department)
September 2026
Finish at recent pace
January 2030
Construction started
September 2024
Registered with the Land Department
July 2024
Developer
Svarn Real Estate Development
Units
94
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
سيرينو ريزيدنسز
Land Department project number
3078
Land Department site inspections
8

Schedule

Sereno Residences was registered to complete in September 2026, 1 month ago, and is still under construction. Over the last year of inspections it has added about 1.9 points a month. Kept at that rate, the site would reach 100% around January 2030.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

3 August 2026

22%+7.2 pts

  • Sereno Residences construction site, Land Department inspection photo 1, 3 August 2026
  • Sereno Residences construction site, Land Department inspection photo 2, 3 August 2026
  • Sereno Residences construction site, Land Department inspection photo 3, 3 August 2026
  • Sereno Residences construction site, Land Department inspection photo 4, 3 August 2026

28 April 2026

15%+5.9 pts

  • Sereno Residences construction site, Land Department inspection photo 1, 28 April 2026
  • Sereno Residences construction site, Land Department inspection photo 2, 28 April 2026
  • Sereno Residences construction site, Land Department inspection photo 3, 28 April 2026
  • Sereno Residences construction site, Land Department inspection photo 4, 28 April 2026

20 January 2026

9.4%+6.3 pts

  • Sereno Residences construction site, Land Department inspection photo 1, 20 January 2026
  • Sereno Residences construction site, Land Department inspection photo 2, 20 January 2026
  • Sereno Residences construction site, Land Department inspection photo 3, 20 January 2026
  • Sereno Residences construction site, Land Department inspection photo 4, 20 January 2026

22 September 2025

3.1%+0.1 pts

  • Sereno Residences construction site, Land Department inspection photo 1, 22 September 2025
  • Sereno Residences construction site, Land Department inspection photo 2, 22 September 2025
  • Sereno Residences construction site, Land Department inspection photo 3, 22 September 2025

29 May 2025

3.0%+0.3 pts

  • Sereno Residences construction site, Land Department inspection photo 1, 29 May 2025
  • Sereno Residences construction site, Land Department inspection photo 2, 29 May 2025
  • Sereno Residences construction site, Land Department inspection photo 3, 29 May 2025

21 January 2025

2.7%+2.1 pts

  • Sereno Residences construction site, Land Department inspection photo 1, 21 January 2025
  • Sereno Residences construction site, Land Department inspection photo 2, 21 January 2025
  • Sereno Residences construction site, Land Department inspection photo 3, 21 January 2025

4 October 2024

0.6%+0.6 pts

  • Sereno Residences construction site, Land Department inspection photo 1, 4 October 2024
  • Sereno Residences construction site, Land Department inspection photo 2, 4 October 2024
  • Sereno Residences construction site, Land Department inspection photo 3, 4 October 2024
  • Sereno Residences construction site, Land Department inspection photo 4, 4 October 2024

28 May 2024

0%

  • Sereno Residences construction site, Land Department inspection photo 1, 28 May 2024
  • Sereno Residences construction site, Land Department inspection photo 2, 28 May 2024
  • Sereno Residences construction site, Land Department inspection photo 3, 28 May 2024

All 33 site photos, by inspection date

Context

Jumeirah Village Circle has 119 projects under construction, 40% built on average.

Own a unit in Sereno Residences?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Sereno Residences be completed?
The completion date registered with the Dubai Land Department is September 2026. At the pace of its recent inspections the site would reach 100% around January 2030. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Sereno Residences is built?
22%, measured at the Land Department site inspection on 3 August 2026. The Land Department engineers have inspected the site 8 times since May 2024.
Is Sereno Residences delayed?
Yes. Its registered completion date of September 2026 has passed and the Land Department still lists it as under construction.
Who is building Sereno Residences?
The registered developer is Svarn Real Estate Development.
Which bank holds the escrow account for Sereno Residences?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.