Sereno Residences construction progress
Sereno Residences in Jumeirah Village Circle was registered to complete in September 2026 and is still under construction. At the last site inspection, in October 2026, it was 32% built. The developer is Svarn Real Estate Development.
32%
Built, at the site inspection of 28 October 2026
3 months past its registered completion date
- Registered completion date
- September 2026
- Finish at recent pace
- February 2029
- Construction started
- September 2024
- First registered
- July 2024
- Developer
- Svarn Real Estate Development
- Community
- Jumeirah Village Circle
- Units
- 94
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- سيرينو ريزيدنسز
- Project number
- 3078
- Site inspections
- 9
Schedule
Sereno Residences was registered to complete in September 2026, 3 months ago, and is still under construction. Over the last year of inspections it has added about 2.5 points a month. Kept at that rate, the site would reach 100% around February 2029.
Site inspections
28 October 2026
32%+9.6 pts
3 August 2026
22%+7.2 pts
28 April 2026
15%+5.9 pts
20 January 2026
9.4%+6.3 pts
22 September 2025
3.1%+0.1 pts
29 May 2025
3.0%+0.3 pts
21 January 2025
2.7%+2.1 pts
4 October 2024
0.6%+0.6 pts
28 May 2024
0%
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
Own a unit in Sereno Residences?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Sereno Residences handover date?
- The registered completion date was September 2026, and the register still lists Sereno Residences as under construction. At the pace of its recent inspections the site would reach 100% around February 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Sereno Residences?
- Sereno Residences was 32% built at the site inspection on 28 October 2026. The site has been inspected 9 times since May 2024. The Land Department took 41 site photos at its inspections.
- Is Sereno Residences delayed?
- Yes. Its registered completion date of September 2026 has passed and the project is still listed as under construction.
- Who is building Sereno Residences?
- The registered developer is Svarn Real Estate Development.
- Which bank holds the escrow account for Sereno Residences?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Aliva GreenNearby in Jumeirah Village Circle. 52%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 91%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)