Sereno Residences construction photos

33 photos taken by Dubai Land Department engineers at 8 site inspections, newest first. The percentage is how much of Sereno Residences was built on the day of each visit.

3 August 202622% built

28 April 202615% built

20 January 20269.4% built

22 September 20253.1% built

29 May 20253.0% built

21 January 20252.7% built

4 October 20240.6% built

28 May 20240% built

Back to Sereno Residences construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.