Sapphire 32 By Dar Alkarama construction progress
Sapphire 32 By Dar Alkarama in Jumeirah Village Circle is 62% built at the Land Department inspection of July 2026. Developer Dar Al Karama Real Estate. Completion registered for December 2026.
62%
Built, at the Land Department site inspection of 10 July 2026
Running behind its date
- Completion date (Land Department)
- December 2026
- Finish at recent pace
- May 2027
- Construction started
- October 2023
- Registered with the Land Department
- October 2023
- Developer
- Dar Al Karama Real Estate
- Community
- Jumeirah Village Circle
- Units
- 232
- Escrow bank
- Sharjah Islamic Bank
- Name in Arabic
- Sapphire 32 By Dar Alkarama
- Land Department project number
- 2757
- Land Department site inspections
- 8
Schedule
Between August 2025 and July 2026 the site added about 3.7 points a month. At that rate it would finish around May 2027, more than three months after the December 2026 date registered with the Land Department.
Site inspections
10 July 2026
62%+0.4 pts
23 March 2026
62%+28 pts
27 November 2025
34%+11 pts
18 August 2025
23%+8.3 pts
24 April 2025
14%+6.5 pts
2 January 2025
8.0%+5.5 pts
30 September 2024
2.5%+2.5 pts
31 August 2023
0%
Context
Jumeirah Village Circle has 119 projects under construction, 40% built on average.
Own a unit in Sapphire 32 By Dar Alkarama?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Sapphire 32 By Dar Alkarama be completed?
- The completion date registered with the Dubai Land Department is December 2026. At the pace of its recent inspections the site would reach 100% around May 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Sapphire 32 By Dar Alkarama is built?
- 62%, measured at the Land Department site inspection on 10 July 2026. The Land Department engineers have inspected the site 8 times since August 2023.
- Is Sapphire 32 By Dar Alkarama delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
- Who is building Sapphire 32 By Dar Alkarama?
- The registered developer is Dar Al Karama Real Estate.
- Which bank holds the escrow account for Sapphire 32 By Dar Alkarama?
- Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 42%, Due January 2013, passed.
- Serenity Lakes 2Nearby in Jumeirah Village Circle. 50%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 90%, Due April 2026, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)














.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)