Skip to content

Sapphire 32 By Dar Alkarama construction progress

The registered completion date for Sapphire 32 By Dar Alkarama in Jumeirah Village Circle is December 2026. At the last site inspection, in November 2026, it was 74% built. The developer is Dar Al Karama Real Estate.

74%

Built, at the site inspection of 10 November 2026

Running behind its date

Registered completion date
December 2026
Finish at recent pace
June 2027
Construction started
October 2023
First registered
October 2023
Developer
Dar Al Karama Real Estate
Units
232
Escrow bank
Sharjah Islamic Bank
Name in Arabic
Sapphire 32 By Dar Alkarama
Project number
2757
Site inspections
9

Schedule

Between November 2025 and November 2026 the site added about 3.5 points a month. At that rate it would finish around June 2027, more than three months after its registered date of December 2026.

0%25%50%75%100%202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

10 November 2026

74%+12 pts

  • Sapphire 32 By Dar Alkarama construction site, inspection photo 1, 10 November 2026
  • Sapphire 32 By Dar Alkarama construction site, inspection photo 2, 10 November 2026
  • Sapphire 32 By Dar Alkarama construction site, inspection photo 3, 10 November 2026
  • Sapphire 32 By Dar Alkarama construction site, inspection photo 4, 10 November 2026

10 July 2026

62%+0.4 pts

  • Sapphire 32 By Dar Alkarama construction site, inspection photo 1, 10 July 2026
  • Sapphire 32 By Dar Alkarama construction site, inspection photo 2, 10 July 2026
  • Sapphire 32 By Dar Alkarama construction site, inspection photo 3, 10 July 2026
  • Sapphire 32 By Dar Alkarama construction site, inspection photo 4, 10 July 2026

23 March 2026

62%+28 pts

27 November 2025

34%+11 pts

  • Sapphire 32 By Dar Alkarama construction site, inspection photo 1, 27 November 2025
  • Sapphire 32 By Dar Alkarama construction site, inspection photo 2, 27 November 2025
  • Sapphire 32 By Dar Alkarama construction site, inspection photo 3, 27 November 2025
  • Sapphire 32 By Dar Alkarama construction site, inspection photo 4, 27 November 2025

18 August 2025

23%+8.3 pts

  • Sapphire 32 By Dar Alkarama construction site, inspection photo 1, 18 August 2025
  • Sapphire 32 By Dar Alkarama construction site, inspection photo 2, 18 August 2025
  • Sapphire 32 By Dar Alkarama construction site, inspection photo 3, 18 August 2025
  • Sapphire 32 By Dar Alkarama construction site, inspection photo 4, 18 August 2025

24 April 2025

14%+6.5 pts

  • Sapphire 32 By Dar Alkarama construction site, inspection photo 1, 24 April 2025
  • Sapphire 32 By Dar Alkarama construction site, inspection photo 2, 24 April 2025
  • Sapphire 32 By Dar Alkarama construction site, inspection photo 3, 24 April 2025
  • Sapphire 32 By Dar Alkarama construction site, inspection photo 4, 24 April 2025

2 January 2025

8.0%+5.5 pts

  • Sapphire 32 By Dar Alkarama construction site, inspection photo 1, 2 January 2025
  • Sapphire 32 By Dar Alkarama construction site, inspection photo 2, 2 January 2025
  • Sapphire 32 By Dar Alkarama construction site, inspection photo 3, 2 January 2025

30 September 2024

2.5%+2.5 pts

  • Sapphire 32 By Dar Alkarama construction site, inspection photo 1, 30 September 2024
  • Sapphire 32 By Dar Alkarama construction site, inspection photo 2, 30 September 2024
  • Sapphire 32 By Dar Alkarama construction site, inspection photo 3, 30 September 2024

31 August 2023

0%

  • Sapphire 32 By Dar Alkarama construction site, inspection photo 1, 31 August 2023
  • Sapphire 32 By Dar Alkarama construction site, inspection photo 2, 31 August 2023
  • Sapphire 32 By Dar Alkarama construction site, inspection photo 3, 31 August 2023

All 65 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Own a unit in Sapphire 32 By Dar Alkarama?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Sapphire 32 By Dar Alkarama handover date?
The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Sapphire 32 By Dar Alkarama?
Sapphire 32 By Dar Alkarama was 74% built at the site inspection on 10 November 2026. The site has been inspected 9 times since August 2023. The Land Department took 65 site photos at its inspections.
Is Sapphire 32 By Dar Alkarama delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building Sapphire 32 By Dar Alkarama?
The registered developer is Dar Al Karama Real Estate.
Which bank holds the escrow account for Sapphire 32 By Dar Alkarama?
Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.