Sapphire 32 By Dar Alkarama construction photos
49 photos taken by Dubai Land Department engineers at 7 site inspections, newest first. The percentage is how much of Sapphire 32 By Dar Alkarama was built on the day of each visit.
10 July 202662% built
27 November 202534% built
18 August 202523% built
24 April 202514% built
2 January 20258.0% built
30 September 20242.5% built
31 August 20230% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.