Samha Residence 2 construction progress
Samha Residence 2 in Jumeirah Village Circle was registered to complete in October 2026 and is still under construction. At the last site inspection, in August 2026, it was 52% built. The developer is Samha Real Estate Development.
52%
Built, at the site inspection of 14 August 2026
1 months past its registered completion date
- Registered completion date
- October 2026
- Finish at recent pace
- November 2027
- Construction started
- February 2025
- First registered
- July 2025
- Developer
- Samha Real Estate Development
- Community
- Jumeirah Village Circle
- Units
- 175
- Escrow bank
- Sharjah Islamic Bank
- Name in Arabic
- سمحه ريزيدنس 2
- Project number
- 3682
- Site inspections
- 4
Schedule
Samha Residence 2 was registered to complete in October 2026, 1 month ago, and is still under construction. Over the last year of inspections it has added about 3.2 points a month. Kept at that rate, the site would reach 100% around November 2027.
Site inspections
14 August 2026
52%+18 pts
25 March 2026
35%+7.3 pts
17 December 2025
27%+12 pts
11 June 2025
15%
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
Own a unit in Samha Residence 2?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Samha Residence 2 handover date?
- The registered completion date was October 2026, and the register still lists Samha Residence 2 as under construction. At the pace of its recent inspections the site would reach 100% around November 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Samha Residence 2?
- Samha Residence 2 was 52% built at the site inspection on 14 August 2026. The site has been inspected 4 times since June 2025. The Land Department took 38 site photos at its inspections.
- Is Samha Residence 2 delayed?
- Yes. Its registered completion date of October 2026 has passed and the project is still listed as under construction.
- Who is building Samha Residence 2?
- The registered developer is Samha Real Estate Development.
- Which bank holds the escrow account for Samha Residence 2?
- Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Aliva GreenNearby in Jumeirah Village Circle. 52%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 91%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.








.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)