Rise Residences construction progress

The register lists Rise Residences in Jumeirah Village Circle as complete, with a registered completion date of August 2025. Its last site inspection on record was in January 2026. The developer is S And S Real Estate Development.

100%

Built, at the site inspection of 5 January 2026

Construction complete

Registered completion date
August 2025
Construction started
August 2023
First registered
September 2023
Developer
S And S Real Estate Development
Units
174
Escrow bank
Sharjah Islamic Bank
Name in Arabic
مساكن الارتفاع
Project number
2731
Site inspections
6

Schedule

The register lists Rise Residences as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

5 January 2026

100%+19 pts

  • Rise Residences construction site, inspection photo 1, 5 January 2026
  • Rise Residences construction site, inspection photo 2, 5 January 2026
  • Rise Residences construction site, inspection photo 3, 5 January 2026
  • Rise Residences construction site, inspection photo 4, 5 January 2026

15 May 2025

81%+20 pts

  • Rise Residences construction site, inspection photo 1, 15 May 2025
  • Rise Residences construction site, inspection photo 2, 15 May 2025
  • Rise Residences construction site, inspection photo 3, 15 May 2025
  • Rise Residences construction site, inspection photo 4, 15 May 2025

27 January 2025

61%+17 pts

  • Rise Residences construction site, inspection photo 1, 27 January 2025
  • Rise Residences construction site, inspection photo 2, 27 January 2025
  • Rise Residences construction site, inspection photo 3, 27 January 2025
  • Rise Residences construction site, inspection photo 4, 27 January 2025

4 November 2024

44%+24 pts

  • Rise Residences construction site, inspection photo 1, 4 November 2024
  • Rise Residences construction site, inspection photo 2, 4 November 2024
  • Rise Residences construction site, inspection photo 3, 4 November 2024
  • Rise Residences construction site, inspection photo 4, 4 November 2024

2 May 2024

20%+20 pts

  • Rise Residences construction site, inspection photo 1, 2 May 2024
  • Rise Residences construction site, inspection photo 2, 2 May 2024

25 July 2023

0%

  • Rise Residences construction site, inspection photo 1, 25 July 2023
  • Rise Residences construction site, inspection photo 2, 25 July 2023
  • Rise Residences construction site, inspection photo 3, 25 July 2023
  • Rise Residences construction site, inspection photo 4, 25 July 2023

All 37 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

S And S Real Estate Development has 1 project under construction in Dubai, none past their registered completion dates.

Own a unit in Rise Residences?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Rise Residences handover date?
Construction of Rise Residences is recorded as complete, with a registered completion date of August 2025. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Rise Residences?
Rise Residences was 100% built at the site inspection on 5 January 2026. The site has been inspected 6 times since July 2023. The Land Department took 37 site photos at its inspections.
Is Rise Residences delayed?
The register lists construction as complete.
Who is building Rise Residences?
The registered developer is S And S Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Rise Residences?
Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.