Lume Residences construction progress
The registered completion date for Lume Residences in Jumeirah Village Circle is September 2027. At the last site inspection, in August 2026, it was 22% built. The developer is S And S Real Estate Development.
22%
Built, at the site inspection of 19 August 2026
Running behind its date
- Registered completion date
- September 2027
- Finish at recent pace
- November 2029
- Construction started
- June 2025
- First registered
- April 2025
- Developer
- S And S Real Estate Development
- Community
- Jumeirah Village Circle
- Units
- 182
- Escrow bank
- Sharjah Islamic Bank
- Name in Arabic
- ريزيدنسز لوم
- Project number
- 3550
- Site inspections
- 4
Schedule
Between October 2025 and August 2026 the site added about 2.0 points a month. At that rate it would finish around November 2029, more than three months after its registered date of September 2027.
Site inspections
19 August 2026
22%+11 pts
1 April 2026
11%+10 pts
2 October 2025
0.4%+0.4 pts
11 February 2025
0%
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
Own a unit in Lume Residences?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Lume Residences handover date?
- The registered completion date is September 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Lume Residences?
- Lume Residences was 22% built at the site inspection on 19 August 2026. The site has been inspected 4 times since February 2025. The Land Department took 21 site photos at its inspections.
- Is Lume Residences delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2027.
- Who is building Lume Residences?
- The registered developer is S And S Real Estate Development.
- Which bank holds the escrow account for Lume Residences?
- Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Aliva GreenNearby in Jumeirah Village Circle. 52%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 91%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)