Skip to content

Lume Residences construction progress

The registered completion date for Lume Residences in Jumeirah Village Circle is September 2027. At the last site inspection, in August 2026, it was 22% built. The developer is S And S Real Estate Development.

22%

Built, at the site inspection of 19 August 2026

Running behind its date

Registered completion date
September 2027
Finish at recent pace
November 2029
Construction started
June 2025
First registered
April 2025
Developer
S And S Real Estate Development
Units
182
Escrow bank
Sharjah Islamic Bank
Name in Arabic
ريزيدنسز لوم
Project number
3550
Site inspections
4

Schedule

Between October 2025 and August 2026 the site added about 2.0 points a month. At that rate it would finish around November 2029, more than three months after its registered date of September 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

19 August 2026

22%+11 pts

  • Lume Residences construction site, inspection photo 1, 19 August 2026
  • Lume Residences construction site, inspection photo 2, 19 August 2026
  • Lume Residences construction site, inspection photo 3, 19 August 2026
  • Lume Residences construction site, inspection photo 4, 19 August 2026

1 April 2026

11%+10 pts

  • Lume Residences construction site, inspection photo 1, 1 April 2026
  • Lume Residences construction site, inspection photo 2, 1 April 2026
  • Lume Residences construction site, inspection photo 3, 1 April 2026
  • Lume Residences construction site, inspection photo 4, 1 April 2026

2 October 2025

0.4%+0.4 pts

  • Lume Residences construction site, inspection photo 1, 2 October 2025
  • Lume Residences construction site, inspection photo 2, 2 October 2025
  • Lume Residences construction site, inspection photo 3, 2 October 2025
  • Lume Residences construction site, inspection photo 4, 2 October 2025

11 February 2025

0%

  • Lume Residences construction site, inspection photo 1, 11 February 2025
  • Lume Residences construction site, inspection photo 2, 11 February 2025

All 21 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Own a unit in Lume Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Lume Residences handover date?
The registered completion date is September 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Lume Residences?
Lume Residences was 22% built at the site inspection on 19 August 2026. The site has been inspected 4 times since February 2025. The Land Department took 21 site photos at its inspections.
Is Lume Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2027.
Who is building Lume Residences?
The registered developer is S And S Real Estate Development.
Which bank holds the escrow account for Lume Residences?
Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.