Palatium Residences construction progress

Palatium Residences in Jumeirah Village Circle was registered to complete in March 2026 and is still under construction. At the last site inspection, in September 2026, it was 88% built. The developer is Ahmadyar Real Estate Development.

88%

Built, at the site inspection of 30 September 2026

8 months past its registered completion date

Registered completion date
March 2026
Finish at recent pace
December 2026
Construction started
May 2024
First registered
July 2024
Developer
Ahmadyar Real Estate Development
Units
151
Escrow bank
First Abu Dhabi Bank
Name in Arabic
بالاشيوم ريزيدنسز
Project number
3065
Site inspections
5

Schedule

Palatium Residences was registered to complete in March 2026, 8 months ago, and is still under construction. Over the last year of inspections it has added about 4.8 points a month. Kept at that rate, the site would reach 100% around December 2026.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

30 September 2026

88%+22 pts

  • Palatium Residences construction site, inspection photo 1, 30 September 2026
  • Palatium Residences construction site, inspection photo 2, 30 September 2026
  • Palatium Residences construction site, inspection photo 3, 30 September 2026
  • Palatium Residences construction site, inspection photo 4, 30 September 2026

19 June 2026

66%+26 pts

  • Palatium Residences construction site, inspection photo 1, 19 June 2026
  • Palatium Residences construction site, inspection photo 2, 19 June 2026
  • Palatium Residences construction site, inspection photo 3, 19 June 2026
  • Palatium Residences construction site, inspection photo 4, 19 June 2026

27 November 2025

40%+23 pts

  • Palatium Residences construction site, inspection photo 1, 27 November 2025
  • Palatium Residences construction site, inspection photo 2, 27 November 2025
  • Palatium Residences construction site, inspection photo 3, 27 November 2025
  • Palatium Residences construction site, inspection photo 4, 27 November 2025

30 May 2025

17%+17 pts

  • Palatium Residences construction site, inspection photo 1, 30 May 2025
  • Palatium Residences construction site, inspection photo 2, 30 May 2025
  • Palatium Residences construction site, inspection photo 3, 30 May 2025
  • Palatium Residences construction site, inspection photo 4, 30 May 2025

15 May 2024

0%

  • Palatium Residences construction site, inspection photo 1, 15 May 2024
  • Palatium Residences construction site, inspection photo 2, 15 May 2024

All 51 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Ahmadyar Real Estate Development has 2 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Palatium Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Palatium Residences handover date?
The registered completion date was March 2026, and the register still lists Palatium Residences as under construction. At the pace of its recent inspections the site would reach 100% around December 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Palatium Residences?
Palatium Residences was 88% built at the site inspection on 30 September 2026. The site has been inspected 5 times since May 2024. The Land Department took 51 site photos at its inspections.
Is Palatium Residences delayed?
Yes. Its registered completion date of March 2026 has passed and the project is still listed as under construction.
Who is building Palatium Residences?
The registered developer is Ahmadyar Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Palatium Residences?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.