Palatium Residences construction progress

Palatium Residences in Jumeirah Village Circle is 88% built at the Land Department inspection of September 2026. Developer Ahmadyar Real Estate Development. Completion registered for March 2026.

88%

Built, at the Land Department site inspection of 30 September 2026

6 months past its registered completion date

Completion date (Land Department)
March 2026
Finish at recent pace
December 2026
Construction started
May 2024
Registered with the Land Department
July 2024
Developer
Ahmadyar Real Estate Development
Units
151
Escrow bank
First Abu Dhabi Bank
Name in Arabic
بالاشيوم ريزيدنسز
Land Department project number
3065
Land Department site inspections
5

Schedule

Palatium Residences was registered to complete in March 2026, 6 months ago, and is still under construction. Over the last year of inspections it has added about 4.8 points a month. Kept at that rate, the site would reach 100% around December 2026.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

30 September 2026

88%+22 pts

  • Palatium Residences construction site, Land Department inspection photo 1, 30 September 2026
  • Palatium Residences construction site, Land Department inspection photo 2, 30 September 2026
  • Palatium Residences construction site, Land Department inspection photo 3, 30 September 2026
  • Palatium Residences construction site, Land Department inspection photo 4, 30 September 2026

19 June 2026

66%+26 pts

  • Palatium Residences construction site, Land Department inspection photo 1, 19 June 2026
  • Palatium Residences construction site, Land Department inspection photo 2, 19 June 2026
  • Palatium Residences construction site, Land Department inspection photo 3, 19 June 2026
  • Palatium Residences construction site, Land Department inspection photo 4, 19 June 2026

27 November 2025

40%+23 pts

  • Palatium Residences construction site, Land Department inspection photo 1, 27 November 2025
  • Palatium Residences construction site, Land Department inspection photo 2, 27 November 2025
  • Palatium Residences construction site, Land Department inspection photo 3, 27 November 2025
  • Palatium Residences construction site, Land Department inspection photo 4, 27 November 2025

30 May 2025

17%+17 pts

  • Palatium Residences construction site, Land Department inspection photo 1, 30 May 2025
  • Palatium Residences construction site, Land Department inspection photo 2, 30 May 2025
  • Palatium Residences construction site, Land Department inspection photo 3, 30 May 2025
  • Palatium Residences construction site, Land Department inspection photo 4, 30 May 2025

15 May 2024

0%

  • Palatium Residences construction site, Land Department inspection photo 1, 15 May 2024
  • Palatium Residences construction site, Land Department inspection photo 2, 15 May 2024

All 51 site photos, by inspection date

Context

Jumeirah Village Circle has 119 projects under construction, 40% built on average.

Ahmadyar Real Estate Development has 2 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Palatium Residences?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Palatium Residences be completed?
The completion date registered with the Dubai Land Department is March 2026. At the pace of its recent inspections the site would reach 100% around December 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Palatium Residences is built?
88%, measured at the Land Department site inspection on 30 September 2026. The Land Department engineers have inspected the site 5 times since May 2024.
Is Palatium Residences delayed?
Yes. Its registered completion date of March 2026 has passed and the Land Department still lists it as under construction.
Who is building Palatium Residences?
The registered developer is Ahmadyar Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Palatium Residences?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.