Vestoria Bay construction progress
The registered completion date for Vestoria Bay in Palm Deira is November 2027. At the last site inspection, in October 2026, it was 3.6% built. The developer is Ahmadyar Real Estate Development.
3.6%
Built, at the site inspection of 2 October 2026
Running behind its date
- Registered completion date
- November 2027
- Finish at recent pace
- August 2054
- Construction started
- November 2025
- First registered
- November 2025
- Developer
- Ahmadyar Real Estate Development
- Community
- Palm Deira
- Units
- 63
- Escrow bank
- Abu Dhabi Islamic Bank
- Name in Arabic
- فيزيتوريا بي
- Project number
- 3858
- Site inspections
- 2
Schedule
Between September 2025 and October 2026 the site added about 0.3 points a month. At that rate it would finish around August 2054, more than three months after its registered date of November 2027.
Site inspections
2 October 2026
3.6%+3.6 pts
16 September 2025
0%
Context
Palm Deira has 94 projects under construction, 24% built on average.
Ahmadyar Real Estate Development has 2 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Vestoria Bay?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Vestoria Bay handover date?
- The registered completion date is November 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2054. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Vestoria Bay?
- Vestoria Bay was 3.6% built at the site inspection on 2 October 2026. The site has been inspected 2 times since September 2025. The Land Department took 8 site photos at its inspections.
- Is Vestoria Bay delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of November 2027.
- Who is building Vestoria Bay?
- The registered developer is Ahmadyar Real Estate Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Vestoria Bay?
- Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Palatium ResidencesAlso by Ahmadyar Real Estate Development. 88%, Due March 2026, passed.
- Bay Residences Dubai IslandsNearby in Palm Deira. 48%, Due October 2026, passed.
- Beach Residences Dubai IslandsNearby in Palm Deira. 29%.
- Bay Villas - Dubai IslandsNearby in Palm Deira. 23%, Due May 2027.
- Edgewater ResidencesNearby in Palm Deira. 48%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.