Norah Residence construction progress

The registered completion date for Norah Residence in Jumeirah Village Circle is June 2027. At the last site inspection, in September 2026, it was 6.8% built. The developer is Al Tareq Star Real Estate Development.

6.8%

Built, at the site inspection of 29 September 2026

Running behind its date

Registered completion date
June 2027
Finish at recent pace
November 2037
Construction started
October 2025
First registered
June 2025
Developer
Al Tareq Star Real Estate Development
Units
184
Escrow bank
Emirates NBD
Name in Arabic
نورا ريزيدنس
Project number
3754
Site inspections
5

Schedule

Between December 2025 and September 2026 the site added about 0.7 points a month. At that rate it would finish around November 2037, more than three months after its registered date of June 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

29 September 2026

6.8%+0.8 pts

  • Norah Residence construction site, inspection photo 1, 29 September 2026
  • Norah Residence construction site, inspection photo 2, 29 September 2026
  • Norah Residence construction site, inspection photo 3, 29 September 2026

2 July 2026

6.0%+0.9 pts

  • Norah Residence construction site, inspection photo 1, 2 July 2026
  • Norah Residence construction site, inspection photo 2, 2 July 2026
  • Norah Residence construction site, inspection photo 3, 2 July 2026
  • Norah Residence construction site, inspection photo 4, 2 July 2026

30 March 2026

5.1%+5.0 pts

  • Norah Residence construction site, inspection photo 1, 30 March 2026
  • Norah Residence construction site, inspection photo 2, 30 March 2026
  • Norah Residence construction site, inspection photo 3, 30 March 2026
  • Norah Residence construction site, inspection photo 4, 30 March 2026

11 December 2025

0.1%+0.1 pts

  • Norah Residence construction site, inspection photo 1, 11 December 2025
  • Norah Residence construction site, inspection photo 2, 11 December 2025

14 May 2025

0%

  • Norah Residence construction site, inspection photo 1, 14 May 2025
  • Norah Residence construction site, inspection photo 2, 14 May 2025

All 16 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Own a unit in Norah Residence?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Norah Residence handover date?
The registered completion date is June 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2037. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Norah Residence?
Norah Residence was 6.8% built at the site inspection on 29 September 2026. The site has been inspected 5 times since May 2025. The Land Department took 16 site photos at its inspections.
Is Norah Residence delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
Who is building Norah Residence?
The registered developer is Al Tareq Star Real Estate Development.
Which bank holds the escrow account for Norah Residence?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.