Norah Residence construction progress
The registered completion date for Norah Residence in Jumeirah Village Circle is June 2027. At the last site inspection, in September 2026, it was 6.8% built. The developer is Al Tareq Star Real Estate Development.
6.8%
Built, at the site inspection of 29 September 2026
Running behind its date
- Registered completion date
- June 2027
- Finish at recent pace
- November 2037
- Construction started
- October 2025
- First registered
- June 2025
- Developer
- Al Tareq Star Real Estate Development
- Community
- Jumeirah Village Circle
- Units
- 184
- Escrow bank
- Emirates NBD
- Name in Arabic
- نورا ريزيدنس
- Project number
- 3754
- Site inspections
- 5
Schedule
Between December 2025 and September 2026 the site added about 0.7 points a month. At that rate it would finish around November 2037, more than three months after its registered date of June 2027.
Site inspections
29 September 2026
6.8%+0.8 pts
2 July 2026
6.0%+0.9 pts
30 March 2026
5.1%+5.0 pts
11 December 2025
0.1%+0.1 pts
14 May 2025
0%
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
Own a unit in Norah Residence?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Norah Residence handover date?
- The registered completion date is June 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2037. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Norah Residence?
- Norah Residence was 6.8% built at the site inspection on 29 September 2026. The site has been inspected 5 times since May 2025. The Land Department took 16 site photos at its inspections.
- Is Norah Residence delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
- Who is building Norah Residence?
- The registered developer is Al Tareq Star Real Estate Development.
- Which bank holds the escrow account for Norah Residence?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Aliva GreenNearby in Jumeirah Village Circle. 52%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 91%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.