Nexara Tower construction progress

The registered completion date for Nexara Tower in Jumeirah Village Circle is April 2028. At the last site inspection, in September 2026, it was 20% built. The developer is Seventh Key Gateway Real Estate Development.

20%

Built, at the site inspection of 15 September 2026

Running behind its date

Registered completion date
April 2028
Finish at recent pace
December 2031
Construction started
April 2025
First registered
June 2025
Developer
Seventh Key Gateway Real Estate Development
Units
187
Escrow bank
Zand Bank
Name in Arabic
نيكسارا تاور
Project number
3584
Site inspections
4

Schedule

Between October 2025 and September 2026 the site added about 1.3 points a month. At that rate it would finish around December 2031, more than three months after its registered date of April 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

15 September 2026

20%+4.3 pts

  • Nexara Tower construction site, inspection photo 1, 15 September 2026
  • Nexara Tower construction site, inspection photo 2, 15 September 2026
  • Nexara Tower construction site, inspection photo 3, 15 September 2026
  • Nexara Tower construction site, inspection photo 4, 15 September 2026

21 May 2026

16%+9.9 pts

  • Nexara Tower construction site, inspection photo 1, 21 May 2026
  • Nexara Tower construction site, inspection photo 2, 21 May 2026
  • Nexara Tower construction site, inspection photo 3, 21 May 2026
  • Nexara Tower construction site, inspection photo 4, 21 May 2026

13 October 2025

5.9%+5.9 pts

  • Nexara Tower construction site, inspection photo 1, 13 October 2025
  • Nexara Tower construction site, inspection photo 2, 13 October 2025
  • Nexara Tower construction site, inspection photo 3, 13 October 2025
  • Nexara Tower construction site, inspection photo 4, 13 October 2025

22 April 2025

0%

  • Nexara Tower construction site, inspection photo 1, 22 April 2025
  • Nexara Tower construction site, inspection photo 2, 22 April 2025

All 19 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Own a unit in Nexara Tower?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Nexara Tower handover date?
The registered completion date is April 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2031. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Nexara Tower?
Nexara Tower was 20% built at the site inspection on 15 September 2026. The site has been inspected 4 times since April 2025. The Land Department took 19 site photos at its inspections.
Is Nexara Tower delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of April 2028.
Who is building Nexara Tower?
The registered developer is Seventh Key Gateway Real Estate Development.
Which bank holds the escrow account for Nexara Tower?
Zand Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.