Nexara Tower construction progress
The registered completion date for Nexara Tower in Jumeirah Village Circle is April 2028. At the last site inspection, in September 2026, it was 20% built. The developer is Seventh Key Gateway Real Estate Development.
20%
Built, at the site inspection of 15 September 2026
Running behind its date
- Registered completion date
- April 2028
- Finish at recent pace
- December 2031
- Construction started
- April 2025
- First registered
- June 2025
- Developer
- Seventh Key Gateway Real Estate Development
- Community
- Jumeirah Village Circle
- Units
- 187
- Escrow bank
- Zand Bank
- Name in Arabic
- نيكسارا تاور
- Project number
- 3584
- Site inspections
- 4
Schedule
Between October 2025 and September 2026 the site added about 1.3 points a month. At that rate it would finish around December 2031, more than three months after its registered date of April 2028.
Site inspections
15 September 2026
20%+4.3 pts
21 May 2026
16%+9.9 pts
13 October 2025
5.9%+5.9 pts
22 April 2025
0%
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
Own a unit in Nexara Tower?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Nexara Tower handover date?
- The registered completion date is April 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2031. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Nexara Tower?
- Nexara Tower was 20% built at the site inspection on 15 September 2026. The site has been inspected 4 times since April 2025. The Land Department took 19 site photos at its inspections.
- Is Nexara Tower delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of April 2028.
- Who is building Nexara Tower?
- The registered developer is Seventh Key Gateway Real Estate Development.
- Which bank holds the escrow account for Nexara Tower?
- Zand Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Aliva GreenNearby in Jumeirah Village Circle. 52%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 91%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.