Nexara Tower construction progress
Nexara Tower in Jumeirah Village Circle is 20% built at the Land Department inspection of September 2026. Developer Seventh Key Gateway Real Estate Development. Completion registered for April 2028.
20%
Built, at the Land Department site inspection of 15 September 2026
Running behind its date
- Completion date (Land Department)
- April 2028
- Finish at recent pace
- December 2031
- Construction started
- April 2025
- Registered with the Land Department
- June 2025
- Developer
- Seventh Key Gateway Real Estate Development
- Community
- Jumeirah Village Circle
- Units
- 187
- Escrow bank
- Zand Bank
- Name in Arabic
- نيكسارا تاور
- Land Department project number
- 3584
- Land Department site inspections
- 4
Schedule
Between October 2025 and September 2026 the site added about 1.3 points a month. At that rate it would finish around December 2031, more than three months after the April 2028 date registered with the Land Department.
Site inspections
15 September 2026
20%+4.3 pts
21 May 2026
16%+9.9 pts
13 October 2025
5.9%+5.9 pts
22 April 2025
0%
Context
Jumeirah Village Circle has 119 projects under construction, 40% built on average.
Own a unit in Nexara Tower?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Nexara Tower be completed?
- The completion date registered with the Dubai Land Department is April 2028. At the pace of its recent inspections the site would reach 100% around December 2031. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Nexara Tower is built?
- 20%, measured at the Land Department site inspection on 15 September 2026. The Land Department engineers have inspected the site 4 times since April 2025.
- Is Nexara Tower delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of April 2028.
- Who is building Nexara Tower?
- The registered developer is Seventh Key Gateway Real Estate Development.
- Which bank holds the escrow account for Nexara Tower?
- Zand Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 42%, Due January 2013, passed.
- Serenity Lakes 2Nearby in Jumeirah Village Circle. 50%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 90%, Due April 2026, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.