Lucky Residence construction progress

The register lists Lucky Residence in Jumeirah Village Circle as complete, with a registered completion date of March 2022. Its last site inspection on record was in August 2022. The developer is Lucky Aeon Real Estate Development.

100%

Built, at the site inspection of 3 August 2022

Construction complete

Registered completion date
March 2022
Construction started
October 2018
First registered
May 2020
Developer
Lucky Aeon Real Estate Development
Units
142
Escrow bank
Mashreq Bank
Name in Arabic
لكي ريزيدنس
Project number
2197
Site inspections
7

Schedule

The register lists Lucky Residence as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2019202020212022
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

3 August 2022

100%+1.2 pts

  • Lucky Residence construction site, inspection photo 1, 3 August 2022
  • Lucky Residence construction site, inspection photo 2, 3 August 2022
  • Lucky Residence construction site, inspection photo 3, 3 August 2022
  • Lucky Residence construction site, inspection photo 4, 3 August 2022

7 July 2022

99%+6.3 pts

  • Lucky Residence construction site, inspection photo 1, 7 July 2022
  • Lucky Residence construction site, inspection photo 2, 7 July 2022
  • Lucky Residence construction site, inspection photo 3, 7 July 2022
  • Lucky Residence construction site, inspection photo 4, 7 July 2022

20 January 2022

93%+6.5 pts

  • Lucky Residence construction site, inspection photo 1, 20 January 2022
  • Lucky Residence construction site, inspection photo 2, 20 January 2022
  • Lucky Residence construction site, inspection photo 3, 20 January 2022
  • Lucky Residence construction site, inspection photo 4, 20 January 2022

27 July 2021

86%+25 pts

  • Lucky Residence construction site, inspection photo 1, 27 July 2021
  • Lucky Residence construction site, inspection photo 2, 27 July 2021
  • Lucky Residence construction site, inspection photo 3, 27 July 2021
  • Lucky Residence construction site, inspection photo 4, 27 July 2021

1 March 2021

61%+18 pts

  • Lucky Residence construction site, inspection photo 1, 1 March 2021
  • Lucky Residence construction site, inspection photo 2, 1 March 2021
  • Lucky Residence construction site, inspection photo 3, 1 March 2021
  • Lucky Residence construction site, inspection photo 4, 1 March 2021

20 October 2020

43%+18 pts

  • Lucky Residence construction site, inspection photo 1, 20 October 2020
  • Lucky Residence construction site, inspection photo 2, 20 October 2020
  • Lucky Residence construction site, inspection photo 3, 20 October 2020
  • Lucky Residence construction site, inspection photo 4, 20 October 2020

27 November 2019

26%

  • Lucky Residence construction site, inspection photo 1, 27 November 2019
  • Lucky Residence construction site, inspection photo 2, 27 November 2019
  • Lucky Residence construction site, inspection photo 3, 27 November 2019
  • Lucky Residence construction site, inspection photo 4, 27 November 2019

All 71 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Lucky Aeon Real Estate Development has 1 project under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Lucky Residence?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Lucky Residence handover date?
Construction of Lucky Residence is recorded as complete, with a registered completion date of March 2022. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Lucky Residence?
Lucky Residence was 100% built at the site inspection on 3 August 2022. The site has been inspected 7 times since November 2019. The Land Department took 71 site photos at its inspections.
Is Lucky Residence delayed?
The register lists construction as complete.
Who is building Lucky Residence?
The registered developer is Lucky Aeon Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Lucky Residence?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.