Lucky Oasis Residence construction progress
Lucky Oasis Residence in Jumeirah Village Circle is 20% built at the Land Department inspection of May 2026. Developer Lucky Aeon Real Estate Development. Completion registered for June 2026.
20%
Built, at the Land Department site inspection of 7 May 2026
3 months past its registered completion date
- Completion date (Land Department)
- June 2026
- Finish at recent pace
- July 2032
- Construction started
- June 2024
- Registered with the Land Department
- May 2024
- Developer
- Lucky Aeon Real Estate Development
- Community
- Jumeirah Village Circle
- Units
- 144
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- لكي اويسس ريسيدنس
- Land Department project number
- 2888
- Land Department site inspections
- 4
Schedule
Lucky Oasis Residence was registered to complete in June 2026, 3 months ago, and is still under construction. Over the last year of inspections it has added about 1.1 points a month. Kept at that rate, the site would reach 100% around July 2032.
Site inspections
7 May 2026
20%+5.4 pts
27 January 2026
15%+6.0 pts
18 June 2025
8.6%+8.6 pts
12 January 2024
0%
Context
Jumeirah Village Circle has 119 projects under construction, 40% built on average.
Lucky Aeon Real Estate Development has 2 projects under construction in Dubai; 2 have passed their registered completion date.
Own a unit in Lucky Oasis Residence?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Lucky Oasis Residence be completed?
- The completion date registered with the Dubai Land Department is June 2026. At the pace of its recent inspections the site would reach 100% around July 2032. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Lucky Oasis Residence is built?
- 20%, measured at the Land Department site inspection on 7 May 2026. The Land Department engineers have inspected the site 4 times since January 2024.
- Is Lucky Oasis Residence delayed?
- Yes. Its registered completion date of June 2026 has passed and the Land Department still lists it as under construction.
- Who is building Lucky Oasis Residence?
- The registered developer is Lucky Aeon Real Estate Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Lucky Oasis Residence?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Lucky Royale ResidenceAlso by Lucky Aeon Real Estate Development. 98%, Due December 2025, passed.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 42%, Due January 2013, passed.
- Serenity Lakes 2Nearby in Jumeirah Village Circle. 50%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 90%, Due April 2026, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.





.jpeg&w=3840&q=75)


.jpg&w=3840&q=75)

.jpg&w=3840&q=75)

.jpeg&w=3840&q=75)