Lucky Oasis Residence construction progress

Lucky Oasis Residence in Jumeirah Village Circle is 20% built at the Land Department inspection of May 2026. Developer Lucky Aeon Real Estate Development. Completion registered for June 2026.

20%

Built, at the Land Department site inspection of 7 May 2026

3 months past its registered completion date

Completion date (Land Department)
June 2026
Finish at recent pace
July 2032
Construction started
June 2024
Registered with the Land Department
May 2024
Developer
Lucky Aeon Real Estate Development
Units
144
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
لكي اويسس ريسيدنس
Land Department project number
2888
Land Department site inspections
4

Schedule

Lucky Oasis Residence was registered to complete in June 2026, 3 months ago, and is still under construction. Over the last year of inspections it has added about 1.1 points a month. Kept at that rate, the site would reach 100% around July 2032.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

7 May 2026

20%+5.4 pts

  • Lucky Oasis Residence construction site, Land Department inspection photo 1, 7 May 2026
  • Lucky Oasis Residence construction site, Land Department inspection photo 2, 7 May 2026
  • Lucky Oasis Residence construction site, Land Department inspection photo 3, 7 May 2026
  • Lucky Oasis Residence construction site, Land Department inspection photo 4, 7 May 2026

27 January 2026

15%+6.0 pts

  • Lucky Oasis Residence construction site, Land Department inspection photo 1, 27 January 2026
  • Lucky Oasis Residence construction site, Land Department inspection photo 2, 27 January 2026
  • Lucky Oasis Residence construction site, Land Department inspection photo 3, 27 January 2026
  • Lucky Oasis Residence construction site, Land Department inspection photo 4, 27 January 2026

18 June 2025

8.6%+8.6 pts

  • Lucky Oasis Residence construction site, Land Department inspection photo 1, 18 June 2025
  • Lucky Oasis Residence construction site, Land Department inspection photo 2, 18 June 2025
  • Lucky Oasis Residence construction site, Land Department inspection photo 3, 18 June 2025
  • Lucky Oasis Residence construction site, Land Department inspection photo 4, 18 June 2025

12 January 2024

0%

  • Lucky Oasis Residence construction site, Land Department inspection photo 1, 12 January 2024
  • Lucky Oasis Residence construction site, Land Department inspection photo 2, 12 January 2024
  • Lucky Oasis Residence construction site, Land Department inspection photo 3, 12 January 2024

All 21 site photos, by inspection date

Context

Jumeirah Village Circle has 119 projects under construction, 40% built on average.

Lucky Aeon Real Estate Development has 2 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Lucky Oasis Residence?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Lucky Oasis Residence be completed?
The completion date registered with the Dubai Land Department is June 2026. At the pace of its recent inspections the site would reach 100% around July 2032. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Lucky Oasis Residence is built?
20%, measured at the Land Department site inspection on 7 May 2026. The Land Department engineers have inspected the site 4 times since January 2024.
Is Lucky Oasis Residence delayed?
Yes. Its registered completion date of June 2026 has passed and the Land Department still lists it as under construction.
Who is building Lucky Oasis Residence?
The registered developer is Lucky Aeon Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Lucky Oasis Residence?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.