Havelock Heights construction progress

Havelock Heights in Jumeirah Village Circle was registered to complete in September 2026 and is still under construction. At the last site inspection, in October 2026, it was 40% built. The developer is Aa And Hmb Real Estate Development.

40%

Built, at the site inspection of 8 October 2026

2 months past its registered completion date

Registered completion date
September 2026
Finish at recent pace
May 2028
Construction started
September 2024
First registered
July 2024
Units
156
Escrow bank
United Bank Limited
Name in Arabic
هافلوك هايتس
Project number
3135
Site inspections
6

Schedule

Havelock Heights was registered to complete in September 2026, 2 months ago, and is still under construction. Over the last year of inspections it has added about 3.2 points a month. Kept at that rate, the site would reach 100% around May 2028.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

8 October 2026

40%+12 pts

  • Havelock Heights construction site, inspection photo 1, 8 October 2026
  • Havelock Heights construction site, inspection photo 2, 8 October 2026
  • Havelock Heights construction site, inspection photo 3, 8 October 2026
  • Havelock Heights construction site, inspection photo 4, 8 October 2026

25 June 2026

28%+9.2 pts

  • Havelock Heights construction site, inspection photo 1, 25 June 2026
  • Havelock Heights construction site, inspection photo 2, 25 June 2026
  • Havelock Heights construction site, inspection photo 3, 25 June 2026
  • Havelock Heights construction site, inspection photo 4, 25 June 2026

18 March 2026

19%+9.4 pts

  • Havelock Heights construction site, inspection photo 1, 18 March 2026
  • Havelock Heights construction site, inspection photo 2, 18 March 2026
  • Havelock Heights construction site, inspection photo 3, 18 March 2026
  • Havelock Heights construction site, inspection photo 4, 18 March 2026

7 October 2025

9.4%+3.9 pts

  • Havelock Heights construction site, inspection photo 1, 7 October 2025
  • Havelock Heights construction site, inspection photo 2, 7 October 2025
  • Havelock Heights construction site, inspection photo 3, 7 October 2025
  • Havelock Heights construction site, inspection photo 4, 7 October 2025

22 May 2025

5.5%+5.5 pts

  • Havelock Heights construction site, inspection photo 1, 22 May 2025
  • Havelock Heights construction site, inspection photo 2, 22 May 2025
  • Havelock Heights construction site, inspection photo 3, 22 May 2025
  • Havelock Heights construction site, inspection photo 4, 22 May 2025

12 June 2024

0%

  • Havelock Heights construction site, inspection photo 1, 12 June 2024
  • Havelock Heights construction site, inspection photo 2, 12 June 2024

All 35 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Aa And Hmb Real Estate Development has 3 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Havelock Heights?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Havelock Heights handover date?
The registered completion date was September 2026, and the register still lists Havelock Heights as under construction. At the pace of its recent inspections the site would reach 100% around May 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Havelock Heights?
Havelock Heights was 40% built at the site inspection on 8 October 2026. The site has been inspected 6 times since June 2024. The Land Department took 35 site photos at its inspections.
Is Havelock Heights delayed?
Yes. Its registered completion date of September 2026 has passed and the project is still listed as under construction.
Who is building Havelock Heights?
The registered developer is Aa And Hmb Real Estate Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Havelock Heights?
United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.