Havelock Heights construction progress

Havelock Heights in Jumeirah Village Circle is 28% built at the Land Department inspection of June 2026. Developer Aa And Hmb Real Estate Development. Completion registered for September 2026.

28%

Built, at the Land Department site inspection of 25 June 2026

1 months past its registered completion date

Completion date (Land Department)
September 2026
Finish at recent pace
March 2029
Construction started
September 2024
Registered with the Land Department
July 2024
Units
156
Escrow bank
United Bank Limited
Name in Arabic
هافلوك هايتس
Land Department project number
3135
Land Department site inspections
5

Schedule

Havelock Heights was registered to complete in September 2026, 1 month ago, and is still under construction. Over the last year of inspections it has added about 2.2 points a month. Kept at that rate, the site would reach 100% around March 2029.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

25 June 2026

28%+9.2 pts

  • Havelock Heights construction site, Land Department inspection photo 1, 25 June 2026
  • Havelock Heights construction site, Land Department inspection photo 2, 25 June 2026
  • Havelock Heights construction site, Land Department inspection photo 3, 25 June 2026
  • Havelock Heights construction site, Land Department inspection photo 4, 25 June 2026

18 March 2026

19%+9.4 pts

  • Havelock Heights construction site, Land Department inspection photo 1, 18 March 2026
  • Havelock Heights construction site, Land Department inspection photo 2, 18 March 2026
  • Havelock Heights construction site, Land Department inspection photo 3, 18 March 2026
  • Havelock Heights construction site, Land Department inspection photo 4, 18 March 2026

7 October 2025

9.4%+3.9 pts

  • Havelock Heights construction site, Land Department inspection photo 1, 7 October 2025
  • Havelock Heights construction site, Land Department inspection photo 2, 7 October 2025
  • Havelock Heights construction site, Land Department inspection photo 3, 7 October 2025
  • Havelock Heights construction site, Land Department inspection photo 4, 7 October 2025

22 May 2025

5.5%+5.5 pts

  • Havelock Heights construction site, Land Department inspection photo 1, 22 May 2025
  • Havelock Heights construction site, Land Department inspection photo 2, 22 May 2025
  • Havelock Heights construction site, Land Department inspection photo 3, 22 May 2025
  • Havelock Heights construction site, Land Department inspection photo 4, 22 May 2025

12 June 2024

0%

  • Havelock Heights construction site, Land Department inspection photo 1, 12 June 2024
  • Havelock Heights construction site, Land Department inspection photo 2, 12 June 2024

All 22 site photos, by inspection date

Context

Jumeirah Village Circle has 119 projects under construction, 40% built on average.

Aa And Hmb Real Estate Development has 3 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Havelock Heights?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Havelock Heights be completed?
The completion date registered with the Dubai Land Department is September 2026. At the pace of its recent inspections the site would reach 100% around March 2029. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Havelock Heights is built?
28%, measured at the Land Department site inspection on 25 June 2026. The Land Department engineers have inspected the site 5 times since June 2024.
Is Havelock Heights delayed?
Yes. Its registered completion date of September 2026 has passed and the Land Department still lists it as under construction.
Who is building Havelock Heights?
The registered developer is Aa And Hmb Real Estate Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Havelock Heights?
United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.