Havelock Residences construction progress
The registered completion date for Havelock Residences in Discovery Gardens is December 2026. At the last site inspection, in November 2026, it was 30% built. The developer is Aa And Hmb Real Estate Development.
30%
Built, at the site inspection of 9 November 2026
Running behind its date
- Registered completion date
- December 2026
- Finish at recent pace
- August 2028
- Construction started
- October 2024
- First registered
- September 2024
- Developer
- Aa And Hmb Real Estate Development
- Community
- Discovery Gardens
- Units
- 230
- Escrow bank
- United Bank Limited
- Name in Arabic
- هافلوك ريذيدنس
- Project number
- 3213
- Site inspections
- 6
Schedule
Between March 2026 and November 2026 the site added about 3.2 points a month. At that rate it would finish around August 2028, more than three months after its registered date of December 2026.
Site inspections
9 November 2026
30%+19 pts
6 July 2026
11%+5.6 pts
27 March 2026
5.8%+1.1 pts
6 October 2025
4.7%+4.7 pts
22 May 2025
0%+0.0 pts
31 July 2024
0%
Context
Discovery Gardens has 9 projects under construction, 48% built on average.
Aa And Hmb Real Estate Development has 3 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Havelock Residences?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Havelock Residences handover date?
- The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Havelock Residences?
- Havelock Residences was 30% built at the site inspection on 9 November 2026. The site has been inspected 6 times since July 2024. The Land Department took 28 site photos at its inspections.
- Is Havelock Residences delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
- Who is building Havelock Residences?
- The registered developer is Aa And Hmb Real Estate Development. It has 2 other projects under construction in Dubai.
- Which bank holds the escrow account for Havelock Residences?
- United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Beverly Gardens By Aa And Hmb Real Estate DevelopmentAlso by Aa And Hmb Real Estate Development. 75%.
- Havelock HeightsAlso by Aa And Hmb Real Estate Development. 40%, Due September 2026, passed.
- California By SdNearby in Discovery Gardens. 24%.
- Serene Gardens By PrescottNearby in Discovery Gardens. 62%.
- Serene Gardens 2 By PrescottNearby in Discovery Gardens. 70%.
- California 2 By SdNearby in Discovery Gardens. 34%, Due October 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.





.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)