Havelock Residences construction progress
Havelock Residences in Discovery Gardens is 11% built at the Land Department inspection of July 2026. Developer Aa And Hmb Real Estate Development. Completion registered for December 2026.
11%
Built, at the Land Department site inspection of 6 July 2026
Running behind its date
- Completion date (Land Department)
- December 2026
- Finish at recent pace
- June 2036
- Construction started
- October 2024
- Registered with the Land Department
- September 2024
- Developer
- Aa And Hmb Real Estate Development
- Community
- Discovery Gardens
- Units
- 230
- Escrow bank
- United Bank Limited
- Name in Arabic
- هافلوك ريذيدنس
- Land Department project number
- 3213
- Land Department site inspections
- 5
Schedule
Between October 2025 and July 2026 the site added about 0.7 points a month. At that rate it would finish around June 2036, more than three months after the December 2026 date registered with the Land Department.
Site inspections
6 July 2026
11%+5.6 pts
27 March 2026
5.8%+1.1 pts
6 October 2025
4.7%+4.7 pts
22 May 2025
0%+0.0 pts
31 July 2024
0%
Context
Discovery Gardens has 9 projects under construction, 46% built on average.
Aa And Hmb Real Estate Development has 3 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Havelock Residences?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Havelock Residences be completed?
- The completion date registered with the Dubai Land Department is December 2026. At the pace of its recent inspections the site would reach 100% around June 2036. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Havelock Residences is built?
- 11%, measured at the Land Department site inspection on 6 July 2026. The Land Department engineers have inspected the site 5 times since July 2024.
- Is Havelock Residences delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
- Who is building Havelock Residences?
- The registered developer is Aa And Hmb Real Estate Development. It has 2 other projects under construction in Dubai.
- Which bank holds the escrow account for Havelock Residences?
- United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Beverly Gardens By Aa And Hmb Real Estate DevelopmentAlso by Aa And Hmb Real Estate Development. 75%.
- Havelock HeightsAlso by Aa And Hmb Real Estate Development. 28%, Due September 2026, passed.
- California By SdNearby in Discovery Gardens. 24%.
- Serene Gardens By PrescottNearby in Discovery Gardens. 62%.
- Serene Gardens 2 By PrescottNearby in Discovery Gardens. 70%.
- California 2 By SdNearby in Discovery Gardens. 34%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)