Greygate Residences By Ade construction progress
Greygate Residences By Ade in Jumeirah Village Circle is 6.5% built at the Land Department inspection of July 2026. Developer A D E Properties. Completion registered for March 2028.
6.5%
Built, at the Land Department site inspection of 9 July 2026
Running behind its date
- Completion date (Land Department)
- March 2028
- Finish at recent pace
- May 2043
- Construction started
- November 2024
- Registered with the Land Department
- January 2025
- Developer
- A D E Properties
- Community
- Jumeirah Village Circle
- Units
- 228
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- مساكن غرايجيت بواسطة اية دي اي
- Land Department project number
- 3232
- Land Department site inspections
- 4
Schedule
Between December 2025 and July 2026 the site added about 0.5 points a month. At that rate it would finish around May 2043, more than three months after the March 2028 date registered with the Land Department.
Site inspections
9 July 2026
6.5%+1.5 pts
23 March 2026
5.0%+1.8 pts
3 December 2025
3.2%+3.2 pts
23 October 2024
0%
Context
Jumeirah Village Circle has 119 projects under construction, 40% built on average.
A D E Properties has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Greygate Residences By Ade?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Greygate Residences By Ade be completed?
- The completion date registered with the Dubai Land Department is March 2028. At the pace of its recent inspections the site would reach 100% around May 2043. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Greygate Residences By Ade is built?
- 6.5%, measured at the Land Department site inspection on 9 July 2026. The Land Department engineers have inspected the site 4 times since October 2024.
- Is Greygate Residences By Ade delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2028.
- Who is building Greygate Residences By Ade?
- The registered developer is A D E Properties. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Greygate Residences By Ade?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Bararigate By AdeAlso by A D E Properties. 0%, Due December 2028.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 42%, Due January 2013, passed.
- Serenity Lakes 2Nearby in Jumeirah Village Circle. 50%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 90%, Due April 2026, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)









