Bararigate By Ade construction progress
The registered completion date for Bararigate By Ade is December 2028. At the last site inspection, in October 2026, it was 1.7% built. The developer is A D E Properties.
1.7%
Built, at the site inspection of 20 October 2026
Running behind its date
- Registered completion date
- December 2028
- Finish at recent pace
- December 2079
- Construction started
- January 2026
- First registered
- January 2026
- Developer
- A D E Properties
- Units
- 282
- Escrow bank
- Emirates NBD
- Name in Arabic
- براري جيت بواسطة ايه دي اي
- Project number
- 4221
- Site inspections
- 3
Schedule
Between November 2025 and October 2026 the site added about 0.2 points a month. At that rate it would finish around December 2079, more than three months after its registered date of December 2028.
Site inspections
20 October 2026
1.7%+1.7 pts
16 June 2026
0%
24 November 2025
0%
Context
A D E Properties has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Bararigate By Ade?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Bararigate By Ade handover date?
- The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2079. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Bararigate By Ade?
- Bararigate By Ade was 1.7% built at the site inspection on 20 October 2026. The site has been inspected 3 times since November 2025. The Land Department took 8 site photos at its inspections.
- Is Bararigate By Ade delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
- Who is building Bararigate By Ade?
- The registered developer is A D E Properties. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Bararigate By Ade?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Greygate Residences By AdeAlso by A D E Properties. 11%, Due March 2028.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.