Bararigate By Ade construction progress

The registered completion date for Bararigate By Ade is December 2028. At the last site inspection, in October 2026, it was 1.7% built. The developer is A D E Properties.

1.7%

Built, at the site inspection of 20 October 2026

Running behind its date

Registered completion date
December 2028
Finish at recent pace
December 2079
Construction started
January 2026
First registered
January 2026
Developer
A D E Properties
Units
282
Escrow bank
Emirates NBD
Name in Arabic
براري جيت بواسطة ايه دي اي
Project number
4221
Site inspections
3

Schedule

Between November 2025 and October 2026 the site added about 0.2 points a month. At that rate it would finish around December 2079, more than three months after its registered date of December 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

20 October 2026

1.7%+1.7 pts

  • Bararigate By Ade construction site, inspection photo 1, 20 October 2026
  • Bararigate By Ade construction site, inspection photo 2, 20 October 2026
  • Bararigate By Ade construction site, inspection photo 3, 20 October 2026
  • Bararigate By Ade construction site, inspection photo 4, 20 October 2026

16 June 2026

0%

  • Bararigate By Ade construction site, inspection photo 1, 16 June 2026

24 November 2025

0%

  • Bararigate By Ade construction site, inspection photo 1, 24 November 2025
  • Bararigate By Ade construction site, inspection photo 2, 24 November 2025

All 8 site photos, by inspection date

Context

A D E Properties has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Bararigate By Ade?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Bararigate By Ade handover date?
The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2079. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Bararigate By Ade?
Bararigate By Ade was 1.7% built at the site inspection on 20 October 2026. The site has been inspected 3 times since November 2025. The Land Department took 8 site photos at its inspections.
Is Bararigate By Ade delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
Who is building Bararigate By Ade?
The registered developer is A D E Properties. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Bararigate By Ade?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.