Gateway By Premier Choice construction photos

83 photos from 12 site inspections, newest first. The percentage is how much of Gateway By Premier Choice was built on the day of each visit.

22 September 202668% built

19 June 202667% built

26 February 202667% built

26 November 202557% built

25 August 202552% built

19 May 202545% built

24 February 202536% built

27 November 202423% built

19 August 202413% built

4 May 20241.4% built

30 October 20231.4% built

1 June 20230% built

Back to Gateway By Premier Choice construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.