Gardenia1 & 2 construction progress

The register lists Gardenia1 & 2 in Jumeirah Village Circle as complete, with a registered completion date of June 2023. Its last site inspection on record was in August 2026. The developer is Memon Investments.

100%

Built, at the site inspection of 27 August 2026

Construction complete

Registered completion date
June 2023
Construction started
February 2014
First registered
February 2014
Developer
Memon Investments
Units
172
Escrow bank
Commercial Bank of Dubai
Name in Arabic
Gardenia1 & 2
Project number
647
Site inspections
16

Schedule

The register lists Gardenia1 & 2 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2015201820212024
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

27 August 2026

100%+3.2 pts

  • Gardenia1 & 2 construction site, inspection photo 1, 27 August 2026
  • Gardenia1 & 2 construction site, inspection photo 2, 27 August 2026
  • Gardenia1 & 2 construction site, inspection photo 3, 27 August 2026
  • Gardenia1 & 2 construction site, inspection photo 4, 27 August 2026

29 April 2025

97%+22 pts

  • Gardenia1 & 2 construction site, inspection photo 1, 29 April 2025
  • Gardenia1 & 2 construction site, inspection photo 2, 29 April 2025
  • Gardenia1 & 2 construction site, inspection photo 3, 29 April 2025
  • Gardenia1 & 2 construction site, inspection photo 4, 29 April 2025

15 February 2024

75%+9.4 pts

  • Gardenia1 & 2 construction site, inspection photo 1, 15 February 2024
  • Gardenia1 & 2 construction site, inspection photo 2, 15 February 2024
  • Gardenia1 & 2 construction site, inspection photo 3, 15 February 2024
  • Gardenia1 & 2 construction site, inspection photo 4, 15 February 2024

4 July 2022

65%+1.4 pts

  • Gardenia1 & 2 construction site, inspection photo 1, 4 July 2022
  • Gardenia1 & 2 construction site, inspection photo 2, 4 July 2022
  • Gardenia1 & 2 construction site, inspection photo 3, 4 July 2022
  • Gardenia1 & 2 construction site, inspection photo 4, 4 July 2022

18 July 2021

64%+7.2 pts

  • Gardenia1 & 2 construction site, inspection photo 1, 18 July 2021
  • Gardenia1 & 2 construction site, inspection photo 2, 18 July 2021
  • Gardenia1 & 2 construction site, inspection photo 3, 18 July 2021
  • Gardenia1 & 2 construction site, inspection photo 4, 18 July 2021

15 December 2020

57%+0.6 pts

  • Gardenia1 & 2 construction site, inspection photo 1, 15 December 2020
  • Gardenia1 & 2 construction site, inspection photo 2, 15 December 2020
  • Gardenia1 & 2 construction site, inspection photo 3, 15 December 2020
  • Gardenia1 & 2 construction site, inspection photo 4, 15 December 2020

24 August 2020

56%

  • Gardenia1 & 2 construction site, inspection photo 1, 24 August 2020
  • Gardenia1 & 2 construction site, inspection photo 2, 24 August 2020
  • Gardenia1 & 2 construction site, inspection photo 3, 24 August 2020
  • Gardenia1 & 2 construction site, inspection photo 4, 24 August 2020

24 December 2019

56%+0.3 pts

  • Gardenia1 & 2 construction site, inspection photo 1, 24 December 2019
  • Gardenia1 & 2 construction site, inspection photo 2, 24 December 2019
  • Gardenia1 & 2 construction site, inspection photo 3, 24 December 2019
  • Gardenia1 & 2 construction site, inspection photo 4, 24 December 2019

21 January 2019

56%+7.3 pts

  • Gardenia1 & 2 construction site, inspection photo 1, 21 January 2019
  • Gardenia1 & 2 construction site, inspection photo 2, 21 January 2019
  • Gardenia1 & 2 construction site, inspection photo 3, 21 January 2019
  • Gardenia1 & 2 construction site, inspection photo 4, 21 January 2019

13 February 2018

49%+3.5 pts

  • Gardenia1 & 2 construction site, inspection photo 1, 13 February 2018
  • Gardenia1 & 2 construction site, inspection photo 2, 13 February 2018
  • Gardenia1 & 2 construction site, inspection photo 3, 13 February 2018
  • Gardenia1 & 2 construction site, inspection photo 4, 13 February 2018

All 151 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Own a unit in Gardenia1 & 2?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Gardenia1 & 2 handover date?
Construction of Gardenia1 & 2 is recorded as complete, with a registered completion date of June 2023. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Gardenia1 & 2?
Gardenia1 & 2 was 100% built at the site inspection on 27 August 2026. The site has been inspected 16 times since July 2014. The Land Department took 151 site photos at its inspections.
Is Gardenia1 & 2 delayed?
The register lists construction as complete.
Who is building Gardenia1 & 2?
The registered developer is Memon Investments.
Which bank holds the escrow account for Gardenia1 & 2?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.