151 photos from 16 site inspections, newest first. The percentage is how much of Gardenia1 & 2 was built on the day of each visit.

27 August 2026100% built

29 April 202597% built

15 February 202475% built

4 July 202265% built

18 July 202164% built

15 December 202057% built

24 August 202056% built

24 December 201956% built

21 January 201956% built

13 February 201849% built

25 July 201745% built

5 January 201736% built

14 July 201629% built

19 January 201613% built

6 October 20154.1% built

13 July 20144.0% built

Back to Gardenia1 & 2 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.