Casa Vista Residence By Golden Woods construction progress

Casa Vista Residence By Golden Woods in Jumeirah Village Circle was registered to complete in June 2026 and is still under construction. At the last site inspection, in June 2026, it was 90% built. The developer is Casa Vista & Golden Woods Developers.

90%

Built, at the site inspection of 9 June 2026

5 months past its registered completion date

Registered completion date
June 2026
Finish at recent pace
December 2026
Construction started
March 2024
First registered
June 2024
Developer
Casa Vista & Golden Woods Developers
Units
90
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
كاسا فيستا رسيدانس بجوادن وودز
Project number
2998
Site inspections
4

Schedule

Casa Vista Residence By Golden Woods was registered to complete in June 2026, 5 months ago, and is still under construction. Over the last year of inspections it has added about 1.6 points a month. Kept at that rate, the site would reach 100% around December 2026.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

9 June 2026

90%+12 pts

  • Casa Vista Residence By Golden Woods construction site, inspection photo 1, 9 June 2026
  • Casa Vista Residence By Golden Woods construction site, inspection photo 2, 9 June 2026
  • Casa Vista Residence By Golden Woods construction site, inspection photo 3, 9 June 2026
  • Casa Vista Residence By Golden Woods construction site, inspection photo 4, 9 June 2026

27 October 2025

78%+30 pts

  • Casa Vista Residence By Golden Woods construction site, inspection photo 1, 27 October 2025
  • Casa Vista Residence By Golden Woods construction site, inspection photo 2, 27 October 2025
  • Casa Vista Residence By Golden Woods construction site, inspection photo 3, 27 October 2025
  • Casa Vista Residence By Golden Woods construction site, inspection photo 4, 27 October 2025

28 April 2025

48%+48 pts

  • Casa Vista Residence By Golden Woods construction site, inspection photo 1, 28 April 2025
  • Casa Vista Residence By Golden Woods construction site, inspection photo 2, 28 April 2025
  • Casa Vista Residence By Golden Woods construction site, inspection photo 3, 28 April 2025
  • Casa Vista Residence By Golden Woods construction site, inspection photo 4, 28 April 2025

11 March 2024

0%

  • Casa Vista Residence By Golden Woods construction site, inspection photo 1, 11 March 2024
  • Casa Vista Residence By Golden Woods construction site, inspection photo 2, 11 March 2024

All 29 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Own a unit in Casa Vista Residence By Golden Woods?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Casa Vista Residence By Golden Woods handover date?
The registered completion date was June 2026, and the register still lists Casa Vista Residence By Golden Woods as under construction. At the pace of its recent inspections the site would reach 100% around December 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Casa Vista Residence By Golden Woods?
Casa Vista Residence By Golden Woods was 90% built at the site inspection on 9 June 2026. The site has been inspected 4 times since March 2024. The Land Department took 29 site photos at its inspections.
Is Casa Vista Residence By Golden Woods delayed?
Yes. Its registered completion date of June 2026 has passed and the project is still listed as under construction.
Who is building Casa Vista Residence By Golden Woods?
The registered developer is Casa Vista & Golden Woods Developers.
Which bank holds the escrow account for Casa Vista Residence By Golden Woods?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.