Casa Vista Residence By Golden Woods construction progress
Casa Vista Residence By Golden Woods in Jumeirah Village Circle was registered to complete in June 2026 and is still under construction. At the last site inspection, in June 2026, it was 90% built. The developer is Casa Vista & Golden Woods Developers.
90%
Built, at the site inspection of 9 June 2026
5 months past its registered completion date
- Registered completion date
- June 2026
- Finish at recent pace
- December 2026
- Construction started
- March 2024
- First registered
- June 2024
- Developer
- Casa Vista & Golden Woods Developers
- Community
- Jumeirah Village Circle
- Units
- 90
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- كاسا فيستا رسيدانس بجوادن وودز
- Project number
- 2998
- Site inspections
- 4
Schedule
Casa Vista Residence By Golden Woods was registered to complete in June 2026, 5 months ago, and is still under construction. Over the last year of inspections it has added about 1.6 points a month. Kept at that rate, the site would reach 100% around December 2026.
Site inspections
9 June 2026
90%+12 pts
27 October 2025
78%+30 pts
28 April 2025
48%+48 pts
11 March 2024
0%
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
Own a unit in Casa Vista Residence By Golden Woods?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Casa Vista Residence By Golden Woods handover date?
- The registered completion date was June 2026, and the register still lists Casa Vista Residence By Golden Woods as under construction. At the pace of its recent inspections the site would reach 100% around December 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Casa Vista Residence By Golden Woods?
- Casa Vista Residence By Golden Woods was 90% built at the site inspection on 9 June 2026. The site has been inspected 4 times since March 2024. The Land Department took 29 site photos at its inspections.
- Is Casa Vista Residence By Golden Woods delayed?
- Yes. Its registered completion date of June 2026 has passed and the project is still listed as under construction.
- Who is building Casa Vista Residence By Golden Woods?
- The registered developer is Casa Vista & Golden Woods Developers.
- Which bank holds the escrow account for Casa Vista Residence By Golden Woods?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Aliva GreenNearby in Jumeirah Village Circle. 52%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 91%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.