Botanica construction progress

The register lists Botanica in Jumeirah Village Circle as complete, with a registered completion date of April 2016. Its last site inspection on record was in May 2016. The developer is Myra Real Estate Deveiopment.

100%

Built, at the site inspection of 25 May 2016

Construction complete

Registered completion date
April 2016
Construction started
July 2014
First registered
April 2015
Developer
Myra Real Estate Deveiopment
Units
121
Escrow bank
First Abu Dhabi Bank
Name in Arabic
بوتانيكا
Project number
1649
Site inspections
2

Schedule

The register lists Botanica as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20152016
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

25 May 2016

100%+21 pts

  • Botanica construction site, inspection photo 1, 25 May 2016
  • Botanica construction site, inspection photo 2, 25 May 2016
  • Botanica construction site, inspection photo 3, 25 May 2016
  • Botanica construction site, inspection photo 4, 25 May 2016

8 September 2015

79%

  • Botanica construction site, inspection photo 1, 8 September 2015
  • Botanica construction site, inspection photo 2, 8 September 2015
  • Botanica construction site, inspection photo 3, 8 September 2015
  • Botanica construction site, inspection photo 4, 8 September 2015

All 21 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Myra Real Estate Deveiopment has 1 project under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Botanica?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Botanica handover date?
Construction of Botanica is recorded as complete, with a registered completion date of April 2016. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Botanica?
Botanica was 100% built at the site inspection on 25 May 2016. The site has been inspected 2 times since September 2015. The Land Department took 21 site photos at its inspections.
Is Botanica delayed?
The register lists construction as complete.
Who is building Botanica?
The registered developer is Myra Real Estate Deveiopment. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Botanica?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.