Myra Onyx construction progress

Myra Onyx was registered to complete in September 2026 and is still under construction. At the last site inspection, in October 2026, it was 86% built. The developer is Myra Real Estate Deveiopment.

86%

Built, at the site inspection of 9 October 2026

3 months past its registered completion date

Registered completion date
September 2026
Finish at recent pace
January 2027
Construction started
September 2024
First registered
January 2026
Developer
Myra Real Estate Deveiopment
Units
60
Escrow bank
First Abu Dhabi Bank
Name in Arabic
مايرا أونيكس
Project number
4308
Site inspections
3

Schedule

Myra Onyx was registered to complete in September 2026, 3 months ago, and is still under construction. Over the last year of inspections it has added about 4.6 points a month. Kept at that rate, the site would reach 100% around January 2027.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

9 October 2026

86%+19 pts

  • Myra Onyx construction site, inspection photo 1, 9 October 2026
  • Myra Onyx construction site, inspection photo 2, 9 October 2026
  • Myra Onyx construction site, inspection photo 3, 9 October 2026
  • Myra Onyx construction site, inspection photo 4, 9 October 2026

2 July 2026

67%+24 pts

  • Myra Onyx construction site, inspection photo 1, 2 July 2026
  • Myra Onyx construction site, inspection photo 2, 2 July 2026
  • Myra Onyx construction site, inspection photo 3, 2 July 2026
  • Myra Onyx construction site, inspection photo 4, 2 July 2026

25 December 2025

43%

  • Myra Onyx construction site, inspection photo 1, 25 December 2025
  • Myra Onyx construction site, inspection photo 2, 25 December 2025
  • Myra Onyx construction site, inspection photo 3, 25 December 2025
  • Myra Onyx construction site, inspection photo 4, 25 December 2025

All 36 site photos, by inspection date

Context

Own a unit in Myra Onyx?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Myra Onyx handover date?
The registered completion date was September 2026, and the register still lists Myra Onyx as under construction. At the pace of its recent inspections the site would reach 100% around January 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Myra Onyx?
Myra Onyx was 86% built at the site inspection on 9 October 2026. The site has been inspected 3 times since December 2025. The Land Department took 36 site photos at its inspections.
Is Myra Onyx delayed?
Yes. Its registered completion date of September 2026 has passed and the project is still listed as under construction.
Who is building Myra Onyx?
The registered developer is Myra Real Estate Deveiopment.
Which bank holds the escrow account for Myra Onyx?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.