Bloom Towers construction progress

The register lists Bloom Towers in Jumeirah Village Circle as complete, with a registered completion date of August 2020. Its last site inspection on record was in February 2021. The developer is Bloom Heights Properties.

100%

Built, at the site inspection of 16 February 2021

Construction complete

Registered completion date
August 2020
Construction started
October 2017
First registered
April 2017
Developer
Bloom Heights Properties
Units
944
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
بلووم تاورز
Project number
1888
Site inspections
12

Schedule

The register lists Bloom Towers as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2018201920202021
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

16 February 2021

100%+9.5 pts

  • Bloom Towers construction site, inspection photo 1, 16 February 2021
  • Bloom Towers construction site, inspection photo 2, 16 February 2021
  • Bloom Towers construction site, inspection photo 3, 16 February 2021
  • Bloom Towers construction site, inspection photo 4, 16 February 2021

8 October 2020

90%+12 pts

  • Bloom Towers construction site, inspection photo 1, 8 October 2020
  • Bloom Towers construction site, inspection photo 2, 8 October 2020
  • Bloom Towers construction site, inspection photo 3, 8 October 2020
  • Bloom Towers construction site, inspection photo 4, 8 October 2020

22 June 2020

79%+8.4 pts

  • Bloom Towers construction site, inspection photo 1, 22 June 2020
  • Bloom Towers construction site, inspection photo 2, 22 June 2020
  • Bloom Towers construction site, inspection photo 3, 22 June 2020
  • Bloom Towers construction site, inspection photo 4, 22 June 2020

5 March 2020

70%+17 pts

  • Bloom Towers construction site, inspection photo 1, 5 March 2020
  • Bloom Towers construction site, inspection photo 2, 5 March 2020
  • Bloom Towers construction site, inspection photo 3, 5 March 2020
  • Bloom Towers construction site, inspection photo 4, 5 March 2020

18 November 2019

53%+12 pts

  • Bloom Towers construction site, inspection photo 1, 18 November 2019
  • Bloom Towers construction site, inspection photo 2, 18 November 2019
  • Bloom Towers construction site, inspection photo 3, 18 November 2019
  • Bloom Towers construction site, inspection photo 4, 18 November 2019

8 August 2019

40%+13 pts

  • Bloom Towers construction site, inspection photo 1, 8 August 2019
  • Bloom Towers construction site, inspection photo 2, 8 August 2019
  • Bloom Towers construction site, inspection photo 3, 8 August 2019
  • Bloom Towers construction site, inspection photo 4, 8 August 2019

15 April 2019

27%+5.9 pts

  • Bloom Towers construction site, inspection photo 1, 15 April 2019
  • Bloom Towers construction site, inspection photo 2, 15 April 2019
  • Bloom Towers construction site, inspection photo 3, 15 April 2019
  • Bloom Towers construction site, inspection photo 4, 15 April 2019

4 December 2018

21%+3.7 pts

  • Bloom Towers construction site, inspection photo 1, 4 December 2018
  • Bloom Towers construction site, inspection photo 2, 4 December 2018
  • Bloom Towers construction site, inspection photo 3, 4 December 2018
  • Bloom Towers construction site, inspection photo 4, 4 December 2018

28 October 2018

17%+6.8 pts

  • Bloom Towers construction site, inspection photo 1, 28 October 2018
  • Bloom Towers construction site, inspection photo 2, 28 October 2018
  • Bloom Towers construction site, inspection photo 3, 28 October 2018
  • Bloom Towers construction site, inspection photo 4, 28 October 2018

16 July 2018

11%+3.4 pts

  • Bloom Towers construction site, inspection photo 1, 16 July 2018
  • Bloom Towers construction site, inspection photo 2, 16 July 2018
  • Bloom Towers construction site, inspection photo 3, 16 July 2018
  • Bloom Towers construction site, inspection photo 4, 16 July 2018

All 111 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Own a unit in Bloom Towers?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Bloom Towers handover date?
Construction of Bloom Towers is recorded as complete, with a registered completion date of August 2020. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Bloom Towers?
Bloom Towers was 100% built at the site inspection on 16 February 2021. The site has been inspected 12 times since November 2017. The Land Department took 111 site photos at its inspections.
Is Bloom Towers delayed?
The register lists construction as complete.
Who is building Bloom Towers?
The registered developer is Bloom Heights Properties.
Which bank holds the escrow account for Bloom Towers?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.