Bloom Towers construction photos

111 photos from 12 site inspections, newest first. The percentage is how much of Bloom Towers was built on the day of each visit.

16 February 2021100% built

8 October 202090% built

22 June 202079% built

5 March 202070% built

18 November 201953% built

8 August 201940% built

15 April 201927% built

4 December 201821% built

28 October 201817% built

16 July 201811% built

15 April 20187.2% built

9 November 20172.4% built

Back to Bloom Towers construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.