Beverly Residence construction progress

The register lists Beverly Residence in Jumeirah Village Circle as complete, with a registered completion date of May 2020. Its last site inspection on record was in February 2021. The developer is H M B Homes Real Estate Development.

100%

Built, at the site inspection of 11 February 2021

Construction complete

Registered completion date
May 2020
Construction started
June 2017
First registered
May 2018
Units
195
Escrow bank
Mashreq Bank
Name in Arabic
بيفيرلي رسيدانس
Project number
1987
Site inspections
4

Schedule

The register lists Beverly Residence as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2018201920202021
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

11 February 2021

100%+16 pts

  • Beverly Residence construction site, inspection photo 1, 11 February 2021
  • Beverly Residence construction site, inspection photo 2, 11 February 2021
  • Beverly Residence construction site, inspection photo 3, 11 February 2021
  • Beverly Residence construction site, inspection photo 4, 11 February 2021

4 March 2020

84%+30 pts

  • Beverly Residence construction site, inspection photo 1, 4 March 2020
  • Beverly Residence construction site, inspection photo 2, 4 March 2020
  • Beverly Residence construction site, inspection photo 3, 4 March 2020
  • Beverly Residence construction site, inspection photo 4, 4 March 2020

27 March 2019

53%+27 pts

  • Beverly Residence construction site, inspection photo 1, 27 March 2019
  • Beverly Residence construction site, inspection photo 2, 27 March 2019
  • Beverly Residence construction site, inspection photo 3, 27 March 2019
  • Beverly Residence construction site, inspection photo 4, 27 March 2019

25 March 2018

27%

  • Beverly Residence construction site, inspection photo 1, 25 March 2018
  • Beverly Residence construction site, inspection photo 2, 25 March 2018
  • Beverly Residence construction site, inspection photo 3, 25 March 2018
  • Beverly Residence construction site, inspection photo 4, 25 March 2018

All 49 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

H M B Homes Real Estate Development has 4 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Beverly Residence?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Beverly Residence handover date?
Construction of Beverly Residence is recorded as complete, with a registered completion date of May 2020. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Beverly Residence?
Beverly Residence was 100% built at the site inspection on 11 February 2021. The site has been inspected 4 times since March 2018. The Land Department took 49 site photos at its inspections.
Is Beverly Residence delayed?
The register lists construction as complete.
Who is building Beverly Residence?
The registered developer is H M B Homes Real Estate Development. It has 4 other projects under construction in Dubai.
Which bank holds the escrow account for Beverly Residence?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.