Berkeley Square By Prestige One construction progress
The registered completion date for Berkeley Square By Prestige One in Jumeirah Village Circle is March 2028. At the last site inspection, in September 2026, it was 3.0% built. The developer is Prestige Luxe Real Estate Development.
3.0%
Built, at the site inspection of 24 September 2026
Running behind its date
- Registered completion date
- March 2028
- Finish at recent pace
- April 2054
- Construction started
- July 2025
- First registered
- July 2025
- Developer
- Prestige Luxe Real Estate Development
- Community
- Jumeirah Village Circle
- Units
- 241
- Escrow bank
- Emirates NBD
- Name in Arabic
- باركلي سكوير من برستيج ون
- Project number
- 3847
- Site inspections
- 4
Schedule
Between November 2025 and September 2026 the site added about 0.3 points a month. At that rate it would finish around April 2054, more than three months after its registered date of March 2028.
Site inspections
24 September 2026
3.0%
25 June 2026
3.0%+3.0 pts
21 November 2025
0%+0.0 pts
26 June 2025
0%
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
Prestige Luxe Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Berkeley Square By Prestige One?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Berkeley Square By Prestige One handover date?
- The registered completion date is March 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2054. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Berkeley Square By Prestige One?
- Berkeley Square By Prestige One was 3.0% built at the site inspection on 24 September 2026. The site has been inspected 4 times since June 2025. The Land Department took 14 site photos at its inspections.
- Is Berkeley Square By Prestige One delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2028.
- Who is building Berkeley Square By Prestige One?
- The registered developer is Prestige Luxe Real Estate Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Berkeley Square By Prestige One?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Prestige One ResidencesAlso by Prestige Luxe Real Estate Development. 0.1%, Due December 2029.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Aliva GreenNearby in Jumeirah Village Circle. 52%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 91%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.