Skip to content

Berkeley Square By Prestige One construction progress

The registered completion date for Berkeley Square By Prestige One in Jumeirah Village Circle is March 2028. At the last site inspection, in September 2026, it was 3.0% built. The developer is Prestige Luxe Real Estate Development.

3.0%

Built, at the site inspection of 24 September 2026

Running behind its date

Registered completion date
March 2028
Finish at recent pace
April 2054
Construction started
July 2025
First registered
July 2025
Developer
Prestige Luxe Real Estate Development
Units
241
Escrow bank
Emirates NBD
Name in Arabic
باركلي سكوير من برستيج ون
Project number
3847
Site inspections
4

Schedule

Between November 2025 and September 2026 the site added about 0.3 points a month. At that rate it would finish around April 2054, more than three months after its registered date of March 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

24 September 2026

3.0%

  • Berkeley Square By Prestige One construction site, inspection photo 1, 24 September 2026
  • Berkeley Square By Prestige One construction site, inspection photo 2, 24 September 2026
  • Berkeley Square By Prestige One construction site, inspection photo 3, 24 September 2026
  • Berkeley Square By Prestige One construction site, inspection photo 4, 24 September 2026

25 June 2026

3.0%+3.0 pts

  • Berkeley Square By Prestige One construction site, inspection photo 1, 25 June 2026
  • Berkeley Square By Prestige One construction site, inspection photo 2, 25 June 2026
  • Berkeley Square By Prestige One construction site, inspection photo 3, 25 June 2026
  • Berkeley Square By Prestige One construction site, inspection photo 4, 25 June 2026

21 November 2025

0%+0.0 pts

  • Berkeley Square By Prestige One construction site, inspection photo 1, 21 November 2025
  • Berkeley Square By Prestige One construction site, inspection photo 2, 21 November 2025
  • Berkeley Square By Prestige One construction site, inspection photo 3, 21 November 2025
  • Berkeley Square By Prestige One construction site, inspection photo 4, 21 November 2025

26 June 2025

0%

  • Berkeley Square By Prestige One construction site, inspection photo 1, 26 June 2025
  • Berkeley Square By Prestige One construction site, inspection photo 2, 26 June 2025

All 14 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Prestige Luxe Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Berkeley Square By Prestige One?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Berkeley Square By Prestige One handover date?
The registered completion date is March 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2054. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Berkeley Square By Prestige One?
Berkeley Square By Prestige One was 3.0% built at the site inspection on 24 September 2026. The site has been inspected 4 times since June 2025. The Land Department took 14 site photos at its inspections.
Is Berkeley Square By Prestige One delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2028.
Who is building Berkeley Square By Prestige One?
The registered developer is Prestige Luxe Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Berkeley Square By Prestige One?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.