Skip to content

Prestige One Residences construction progress

The registered completion date for Prestige One Residences is December 2029. At the last site inspection, in September 2026, it was 0.1% built. The developer is Prestige Luxe Real Estate Development.

0.1%

Built, at the site inspection of 23 September 2026

Running behind its date

Registered completion date
December 2029
Finish at recent pace
May 2817
Construction started
February 2026
First registered
November 2025
Developer
Prestige Luxe Real Estate Development
Units
220
Escrow bank
Emirates NBD
Name in Arabic
بريستيج ون ريزيدنسز
Project number
4190
Site inspections
3

Schedule

Between November 2025 and September 2026 the site added about 0.0 points a month. At that rate it would finish around May 2817, more than three months after its registered date of December 2029.

0%25%50%75%100%2026202720282029
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

23 September 2026

0.1%+0.1 pts

  • Prestige One Residences construction site, inspection photo 1, 23 September 2026
  • Prestige One Residences construction site, inspection photo 2, 23 September 2026
  • Prestige One Residences construction site, inspection photo 3, 23 September 2026
  • Prestige One Residences construction site, inspection photo 4, 23 September 2026

22 June 2026

0%+0.0 pts

  • Prestige One Residences construction site, inspection photo 1, 22 June 2026
  • Prestige One Residences construction site, inspection photo 2, 22 June 2026
  • Prestige One Residences construction site, inspection photo 3, 22 June 2026
  • Prestige One Residences construction site, inspection photo 4, 22 June 2026

9 November 2025

0%

  • Prestige One Residences construction site, inspection photo 1, 9 November 2025
  • Prestige One Residences construction site, inspection photo 2, 9 November 2025

All 10 site photos, by inspection date

Context

Prestige Luxe Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Prestige One Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Prestige One Residences handover date?
The registered completion date is December 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2817. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Prestige One Residences?
Prestige One Residences was 0.1% built at the site inspection on 23 September 2026. The site has been inspected 3 times since November 2025. The Land Department took 10 site photos at its inspections.
Is Prestige One Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2029.
Who is building Prestige One Residences?
The registered developer is Prestige Luxe Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Prestige One Residences?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.