Azurline Residences By Maas Developers construction progress

The registered completion date for Azurline Residences By Maas Developers in Jumeirah Village Circle is March 2027. At the last site inspection, in September 2026, it was 57% built. The developer is M A A S Developers.

57%

Built, at the site inspection of 28 September 2026

Running behind its date

Registered completion date
March 2027
Finish at recent pace
December 2027
Construction started
January 2025
First registered
March 2025
Developer
M A A S Developers
Units
205
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
أزور لاين ريزيدنس من مااس للتطوير
Project number
3477
Site inspections
5

Schedule

Between December 2025 and September 2026 the site added about 3.0 points a month. At that rate it would finish around December 2027, more than three months after its registered date of March 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

28 September 2026

57%+15 pts

  • Azurline Residences By Maas Developers construction site, inspection photo 1, 28 September 2026
  • Azurline Residences By Maas Developers construction site, inspection photo 2, 28 September 2026
  • Azurline Residences By Maas Developers construction site, inspection photo 3, 28 September 2026
  • Azurline Residences By Maas Developers construction site, inspection photo 4, 28 September 2026

30 April 2026

42%+12 pts

  • Azurline Residences By Maas Developers construction site, inspection photo 1, 30 April 2026
  • Azurline Residences By Maas Developers construction site, inspection photo 2, 30 April 2026
  • Azurline Residences By Maas Developers construction site, inspection photo 3, 30 April 2026
  • Azurline Residences By Maas Developers construction site, inspection photo 4, 30 April 2026

29 December 2025

30%+14 pts

  • Azurline Residences By Maas Developers construction site, inspection photo 1, 29 December 2025
  • Azurline Residences By Maas Developers construction site, inspection photo 2, 29 December 2025
  • Azurline Residences By Maas Developers construction site, inspection photo 3, 29 December 2025
  • Azurline Residences By Maas Developers construction site, inspection photo 4, 29 December 2025

24 July 2025

16%+11 pts

  • Azurline Residences By Maas Developers construction site, inspection photo 1, 24 July 2025
  • Azurline Residences By Maas Developers construction site, inspection photo 2, 24 July 2025
  • Azurline Residences By Maas Developers construction site, inspection photo 3, 24 July 2025
  • Azurline Residences By Maas Developers construction site, inspection photo 4, 24 July 2025

22 January 2025

5.4%

  • Azurline Residences By Maas Developers construction site, inspection photo 1, 22 January 2025
  • Azurline Residences By Maas Developers construction site, inspection photo 2, 22 January 2025
  • Azurline Residences By Maas Developers construction site, inspection photo 3, 22 January 2025
  • Azurline Residences By Maas Developers construction site, inspection photo 4, 22 January 2025

All 35 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Own a unit in Azurline Residences By Maas Developers?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Azurline Residences By Maas Developers handover date?
The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Azurline Residences By Maas Developers?
Azurline Residences By Maas Developers was 57% built at the site inspection on 28 September 2026. The site has been inspected 5 times since January 2025. The Land Department took 35 site photos at its inspections.
Is Azurline Residences By Maas Developers delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
Who is building Azurline Residences By Maas Developers?
The registered developer is M A A S Developers.
Which bank holds the escrow account for Azurline Residences By Maas Developers?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.