Azurline Residences By Maas Developers construction progress
Azurline Residences By Maas Developers in Jumeirah Village Circle is 57% built at the Land Department inspection of September 2026. Developer M A A S Developers. Completion registered for March 2027.
57%
Built, at the Land Department site inspection of 28 September 2026
Running behind its date
- Completion date (Land Department)
- March 2027
- Finish at recent pace
- December 2027
- Construction started
- January 2025
- Registered with the Land Department
- March 2025
- Developer
- M A A S Developers
- Community
- Jumeirah Village Circle
- Units
- 205
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- أزور لاين ريزيدنس من مااس للتطوير
- Land Department project number
- 3477
- Land Department site inspections
- 5
Schedule
Between December 2025 and September 2026 the site added about 3.0 points a month. At that rate it would finish around December 2027, more than three months after the March 2027 date registered with the Land Department.
Site inspections
28 September 2026
57%+15 pts
30 April 2026
42%+12 pts
29 December 2025
30%+14 pts
24 July 2025
16%+11 pts
22 January 2025
5.4%
Context
Jumeirah Village Circle has 119 projects under construction, 40% built on average.
Own a unit in Azurline Residences By Maas Developers?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Azurline Residences By Maas Developers be completed?
- The completion date registered with the Dubai Land Department is March 2027. At the pace of its recent inspections the site would reach 100% around December 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Azurline Residences By Maas Developers is built?
- 57%, measured at the Land Department site inspection on 28 September 2026. The Land Department engineers have inspected the site 5 times since January 2025.
- Is Azurline Residences By Maas Developers delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
- Who is building Azurline Residences By Maas Developers?
- The registered developer is M A A S Developers.
- Which bank holds the escrow account for Azurline Residences By Maas Developers?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 42%, Due January 2013, passed.
- Serenity Lakes 2Nearby in Jumeirah Village Circle. 50%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 90%, Due April 2026, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.