Azurline Residences By Maas Developers construction progress
The registered completion date for Azurline Residences By Maas Developers in Jumeirah Village Circle is March 2027. At the last site inspection, in September 2026, it was 57% built. The developer is M A A S Developers.
57%
Built, at the site inspection of 28 September 2026
Running behind its date
- Registered completion date
- March 2027
- Finish at recent pace
- December 2027
- Construction started
- January 2025
- First registered
- March 2025
- Developer
- M A A S Developers
- Community
- Jumeirah Village Circle
- Units
- 205
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- أزور لاين ريزيدنس من مااس للتطوير
- Project number
- 3477
- Site inspections
- 5
Schedule
Between December 2025 and September 2026 the site added about 3.0 points a month. At that rate it would finish around December 2027, more than three months after its registered date of March 2027.
Site inspections
28 September 2026
57%+15 pts
30 April 2026
42%+12 pts
29 December 2025
30%+14 pts
24 July 2025
16%+11 pts
22 January 2025
5.4%
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
Own a unit in Azurline Residences By Maas Developers?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Azurline Residences By Maas Developers handover date?
- The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Azurline Residences By Maas Developers?
- Azurline Residences By Maas Developers was 57% built at the site inspection on 28 September 2026. The site has been inspected 5 times since January 2025. The Land Department took 35 site photos at its inspections.
- Is Azurline Residences By Maas Developers delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
- Who is building Azurline Residences By Maas Developers?
- The registered developer is M A A S Developers.
- Which bank holds the escrow account for Azurline Residences By Maas Developers?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Aliva GreenNearby in Jumeirah Village Circle. 52%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 91%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.