Azurline Residences By Maas Developers construction photos
35 photos from 5 site inspections, newest first. The percentage is how much of Azurline Residences By Maas Developers was built on the day of each visit.
28 September 202657% built
30 April 202642% built
29 December 202530% built
24 July 202516% built
22 January 20255.4% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.