Astoria Residnece construction progress
The register lists Astoria Residnece in Jumeirah Village Circle as complete, with a registered completion date of May 2016. Its last site inspection on record was in March 2017. The developer is Segrex Limited.
100%
Built, at the site inspection of 21 March 2017
Construction complete
- Registered completion date
- May 2016
- Construction started
- September 2008
- First registered
- November 2008
- Developer
- Segrex Limited
- Community
- Jumeirah Village Circle
- Units
- 77
- Escrow bank
- Emirates NBD
- Name in Arabic
- أستوريا ريزيدنس
- Project number
- 946
- Site inspections
- 6
Schedule
The register lists Astoria Residnece as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
21 March 2017
100%+1.0 pts
4 October 2016
99%+0.2 pts
6 October 2015
99%+26 pts
22 June 2014
73%+0.6 pts
27 January 2014
72%+12 pts
29 April 2013
61%
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
Own a unit in Astoria Residnece?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the Astoria Residnece handover date?
- Construction of Astoria Residnece is recorded as complete, with a registered completion date of May 2016. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on Astoria Residnece?
- Astoria Residnece was 100% built at the site inspection on 21 March 2017. The site has been inspected 6 times since April 2013. The Land Department took 60 site photos at its inspections.
- Is Astoria Residnece delayed?
- The register lists construction as complete.
- Who is building Astoria Residnece?
- The registered developer is Segrex Limited.
- Which bank holds the escrow account for Astoria Residnece?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Aliva GreenNearby in Jumeirah Village Circle. 52%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 91%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.