Skip to content

Astoria Residnece construction progress

The register lists Astoria Residnece in Jumeirah Village Circle as complete, with a registered completion date of May 2016. Its last site inspection on record was in March 2017. The developer is Segrex Limited.

100%

Built, at the site inspection of 21 March 2017

Construction complete

Registered completion date
May 2016
Construction started
September 2008
First registered
November 2008
Developer
Segrex Limited
Units
77
Escrow bank
Emirates NBD
Name in Arabic
أستوريا ريزيدنس
Project number
946
Site inspections
6

Schedule

The register lists Astoria Residnece as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20092011201320152017
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

21 March 2017

100%+1.0 pts

  • Astoria Residnece construction site, inspection photo 1, 21 March 2017
  • Astoria Residnece construction site, inspection photo 2, 21 March 2017
  • Astoria Residnece construction site, inspection photo 3, 21 March 2017
  • Astoria Residnece construction site, inspection photo 4, 21 March 2017

4 October 2016

99%+0.2 pts

  • Astoria Residnece construction site, inspection photo 1, 4 October 2016
  • Astoria Residnece construction site, inspection photo 2, 4 October 2016
  • Astoria Residnece construction site, inspection photo 3, 4 October 2016
  • Astoria Residnece construction site, inspection photo 4, 4 October 2016

6 October 2015

99%+26 pts

  • Astoria Residnece construction site, inspection photo 1, 6 October 2015
  • Astoria Residnece construction site, inspection photo 2, 6 October 2015
  • Astoria Residnece construction site, inspection photo 3, 6 October 2015
  • Astoria Residnece construction site, inspection photo 4, 6 October 2015

22 June 2014

73%+0.6 pts

  • Astoria Residnece construction site, inspection photo 1, 22 June 2014
  • Astoria Residnece construction site, inspection photo 2, 22 June 2014
  • Astoria Residnece construction site, inspection photo 3, 22 June 2014
  • Astoria Residnece construction site, inspection photo 4, 22 June 2014

27 January 2014

72%+12 pts

  • Astoria Residnece construction site, inspection photo 1, 27 January 2014
  • Astoria Residnece construction site, inspection photo 2, 27 January 2014
  • Astoria Residnece construction site, inspection photo 3, 27 January 2014
  • Astoria Residnece construction site, inspection photo 4, 27 January 2014

29 April 2013

61%

  • Astoria Residnece construction site, inspection photo 1, 29 April 2013
  • Astoria Residnece construction site, inspection photo 2, 29 April 2013
  • Astoria Residnece construction site, inspection photo 3, 29 April 2013
  • Astoria Residnece construction site, inspection photo 4, 29 April 2013

All 60 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Own a unit in Astoria Residnece?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Astoria Residnece handover date?
Construction of Astoria Residnece is recorded as complete, with a registered completion date of May 2016. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Astoria Residnece?
Astoria Residnece was 100% built at the site inspection on 21 March 2017. The site has been inspected 6 times since April 2013. The Land Department took 60 site photos at its inspections.
Is Astoria Residnece delayed?
The register lists construction as complete.
Who is building Astoria Residnece?
The registered developer is Segrex Limited.
Which bank holds the escrow account for Astoria Residnece?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.