Al Serh Residences 11 By Asak Real Estate Development construction progress

The register lists Al Serh Residences 11 By Asak Real Estate Development in Jumeirah Village Circle as complete, with a registered completion date of February 2025. Its last site inspection on record was in August 2025. The developer is Asak Real Estate Development.

100%

Built, at the site inspection of 27 August 2025

Construction complete

Registered completion date
February 2025
Construction started
November 2023
First registered
November 2024
Developer
Asak Real Estate Development
Units
105
Escrow bank
Commercial Bank of Dubai
Name in Arabic
مساكن الصرح 11
Project number
3194
Site inspections
3

Schedule

The register lists Al Serh Residences 11 By Asak Real Estate Development as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20242025
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

27 August 2025

100%+9.8 pts

  • Al Serh Residences 11 By Asak Real Estate Development construction site, inspection photo 1, 27 August 2025
  • Al Serh Residences 11 By Asak Real Estate Development construction site, inspection photo 2, 27 August 2025
  • Al Serh Residences 11 By Asak Real Estate Development construction site, inspection photo 3, 27 August 2025
  • Al Serh Residences 11 By Asak Real Estate Development construction site, inspection photo 4, 27 August 2025

12 March 2025

90%+36 pts

  • Al Serh Residences 11 By Asak Real Estate Development construction site, inspection photo 1, 12 March 2025
  • Al Serh Residences 11 By Asak Real Estate Development construction site, inspection photo 2, 12 March 2025
  • Al Serh Residences 11 By Asak Real Estate Development construction site, inspection photo 3, 12 March 2025
  • Al Serh Residences 11 By Asak Real Estate Development construction site, inspection photo 4, 12 March 2025

10 August 2024

54%

  • Al Serh Residences 11 By Asak Real Estate Development construction site, inspection photo 1, 10 August 2024
  • Al Serh Residences 11 By Asak Real Estate Development construction site, inspection photo 2, 10 August 2024
  • Al Serh Residences 11 By Asak Real Estate Development construction site, inspection photo 3, 10 August 2024
  • Al Serh Residences 11 By Asak Real Estate Development construction site, inspection photo 4, 10 August 2024

All 27 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Asak Real Estate Development has 1 project under construction in Dubai, none past their registered completion dates.

Own a unit in Al Serh Residences 11 By Asak Real Estate Development?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Al Serh Residences 11 By Asak Real Estate Development handover date?
Construction of Al Serh Residences 11 By Asak Real Estate Development is recorded as complete, with a registered completion date of February 2025. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Al Serh Residences 11 By Asak Real Estate Development?
Al Serh Residences 11 By Asak Real Estate Development was 100% built at the site inspection on 27 August 2025. The site has been inspected 3 times since August 2024. The Land Department took 27 site photos at its inspections.
Is Al Serh Residences 11 By Asak Real Estate Development delayed?
The register lists construction as complete.
Who is building Al Serh Residences 11 By Asak Real Estate Development?
The registered developer is Asak Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Al Serh Residences 11 By Asak Real Estate Development?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.